The National Gas Company (NGC) is moving to recover from Super Industrial Services Ltd (SIS) the costs of completing the works on the Beetham Wastewater Project and any other losses and damages incurred as a result of SIS's alleged breaches of a billion-dollar contract for the project, Minister in the Ministry of the Attorney General Stuart Young says.
In a statement to Parliament yesterday, Young revealed that NGC, whose mandate was not the provision of water, entered into the contract for over $1 billion and had paid out over $780 million to SIS to date–about 75 per cent of the full cost–when only approximately 40-45 per cent of the project work was completed.
With the impending termination of the SIS contract effective December 4, Young, relating details of what had led to this, added: "An assessment is being conducted by the new NGC board to decide what are the next steps to be taken with respect to this project that has cost over $780 million. Options include commencement of arbitration proceedings to recover damages incurred and the costs associated with the completion of the project. When a decision is taken with respect to the future progress of this project we'll inform the public."
The NGC, under the past People's Partnership (PP) administration's tenure, had awarded a contract to SIS for the design and build of the plant, together with the associated pipelines and water storage facilities. The purpose of the project was to recycle output water from WASA's existing wastewater treatment plant to industrial water quality standard and to take the pipe-treated water from Beetham to the Pt Lisas Industrial Estate using newly built pipeline infrastructure.
Young said requests for proposals for the project were issued on December 10, 2013. The contract was issued on March 10, 2014, in the sum of approximately TT$1,037,154,560.00 (USD$162,055,319).
He said, "It's noteworthy that SIS wasn't the lowest bidder on this project. In fact, SIS's bid was TT$464,196,390 (USD$72,530,686) more than the other bidder.
"It's also noteworthy, the last administration paid a 20 per cent mobilisation to SIS. It is not usual to have as high as a 20 per cent mobilisation fee. In this case, NGC made an advance payment to SIS which was TT$207,430,810.00 (USD$32,411,064).
"A mobilisation fee is usually worked back through the life of a contract, with appropriate credit or repayment being given to the employer as the contract is performed. To date, none of this mobilisation/advance payment, of some TT$207,430,810.00, has been repaid (or credited) to NGC by SIS."
Further, Young said, to date NGC has paid SIS the sum of approximately $780 million (USD$121,745,121.64), with the last payment certificate certified by NGC being for work done in May 2015.
He said on October 8, 2014, SIS was awarded a further contract by NGC for operation and management of the Beetham Water Recycling Plant for a five-year period with a value of approximately $56.4 million.
"This contract was only for the Beetham plant and not the pipeline to Pt Lisas nor the storage at Pt Lisas. The question is why was NGC utilised as the entity to contract SIS for the design/build of this billion-dollar water provision facility as opposed to WASA? WASA is the statutory body charged with the responsibility for water supply," he said.
"It has also been discovered that to date, there is no 'off take contract' entered into for the final water product from this project. Therefore, NGC, whose mandate was not and is not the provision of water, entered into this contract for over TT$1 billion, paying out over TT$780 million to SIS to date, and only approximately 40-45 per cent of the project work is completed, when over 75 per cent of the full cost of the project has already been expended from the cash coffers of NGC."
Young said the new NGC board was having an independent assessment done of the works performed to ascertain the quantum and percentage of work actually performed, since this was necessary due to the circumstances. He said SIS began slowing down works prior to the general election and this became even more apparent after the September 7 general election.
"After elections, NGC received several reports from the sub-contractors of SIS as to non-payment of monies due to them by SIS. On September 14, 2015 (one week after the elections), SIS wrote to NGC in an attempt to extricate itself from its contractual obligations, after having already been paid $780 million and only completing 40-45 per cent of the works."
(With reporting by Renuka Singh)
SIS claims govt interference
Minister in the Ministry of the Attorney General, Stuart Young, also said yesterday that SIS, in discussions about the controversial project, claimed, "...people now holding high office in the Government...have made serious allegations about the project and the conduct of officials of NGC and SIS."
As a result, he said SIS stated it was "...reasonably certain that steps would now be taken by the State to stop or frustrate SIS in the successful execution of this project."
Young added, "SIS used this as one of its reasons for slowing down works and eventually refusing to continue the project. (But) There was no evidence to support this position that the new Government would have stopped or frustrated SIS from completing the project."
He said NGC denied any allegations of state interference and stated it was committed to enforcement of the contract and it expected SIS to continue to deliver all contractual obligations in a responsible and timely manner.
Young added, "There then ensued an exchange of correspondence and communications between SIS and NGC, wherein SIS claimed that it had underbid on the project at the tender stage and it was unable to continue the works without a review of the contract price and project schedule and that it could no longer fund the works. This, even though SIS's price for the project was TT$464 million more than the next bidder.
"SIS also suddenly claimed it had safety and security threats and it used this as its excuse to begin the withdrawal of construction resources, manpower and equipment from the sites on October 8, 2015," he said.
"Despite the exchanges and discussions between the parties, SIS refused to renew the performance payment bond and the insurance coverage that it was contractually obligated to renew; this left NGC exposed. Ultimately, SIS indicated it would only complete the project on new terms and conditions, including a new project schedule, all whilst it withdrew from the project sites.
"As a result of these developments, NGC, under direction of its new board sought and obtained independent legal advice and moved quickly to protect NGC's position (and the position of the citizens) with some $780 million having already been expended.
"On Friday, 20 November, after due and proper consideration of the facts, failed attempts to discuss the way forward and the advice obtained, NGC gave SIS written notice of its intention to terminate the design/build contract."
He said, NGC, in recapping SIS's position that it was unable to continue with the works, drew attention to actions by SIS that "demonstrated that SIS had abandoned the works or alternatively did not intend to continue performance of its obligations under the contract."
The company was founded by businessman Krishna Lalla, who divested the majority of his holdings to sons Terrence and Lincoln Lalla. Early last year both sons were listed as the owners of the company and media reports listed Terrence as the main owner of the company
But in a brief telephone interview yesterday, Terrence Lalla distanced himself from SIS.
"I am no longer involved with SIS's business," Lalla said.
"I no longer have anything to do with SIS and cannot even direct you who to talk to there," Lalla added.