Clarify construction confusion

Published: 3 Dec 2009

The more information made available on the Government’s construction programme, the more confusing the situation becomes. So too do the explanations surrounding the escalation in costs become wondrous to those sitting on the sidelines, perhaps unaware as the Government and its construction driver, Udecott, continue merrily ahead.

Let us start with the National Academy for the Performing Arts, the north facility that is. At the opening ceremony for the facility, Prime Minister Patrick Manning announced proudly that the academy had been completed within budget and on time. However, on Tuesday this week, Planning Minister Dick-Forde went to the Senate and said the original completion date for the academy (north) was December 2008, which means the facility was a full 11 months behind schedule. The minister also announced that the original cost of the academy was US$60 million—approximately $378 million. However, Prime Minister Manning’s figure worked out to be approximately $500 million. Unfortunately, Minister Dick-Forde did not offer information about the varying costs and dates to explain the major discrepancies. However, the minister did give a few reasons for minor cost escalation. With regard to the Port-of-Spain academy, she listed demolition and replacement of the old tennis courts from the site to the King George V Park. Now this is a quite baffling explanation which raises further questions. Was it that the original plan was to simply flatten the tennis courts and not replace them? If the answer is “yes,” then is it that the Government was completely unconcerned for sporting facilities, including netball and hockey, used by thousands of people?

But if the answer is “no,” then what incompetence on the part of the planners and those who developed the cost package to construct the academy. How could they have not budgeted for the destruction and restoration of those very visible sporting facilities? With regard to the south academy, there is also the unexplained variation in projected costs and actual costs. The Prime Minister, speaking at the launch, said that this facility would cost approximately $320 million compared to the approximately $240 million figure given by the minister. There is also the significant shift in the completion time by over 12 months. Here again we are faced with a few incredible items which were not originally catered for, among them the relocation of a sewer line. How could the designers have drawn up plans and not catered for the removal of such a line? Also, what has not been given by either the Prime Minister or his Planning Minister is a breakdown indicating change in plans, additions to original designs and other factors which would explain why the cost escalation and time overruns on both projects.

This information is important because the Government and Udecott have damned the local construction industry for similar kinds of overruns of time and escalation in prices when a number of the local contractors have blamed the delays and cost escalation on the Government for changing designs and adding to the size of the projects. Clarification on these matters has to be made as the Government comes before the bar of public opinion to argue its case for its preference of foreign contractors. This is undoubtedly the largest and most expensive construction programme ever engaged in this country. The resources are part of the patrimony of the country, and not merely for this generation and those living at the moment, but of those generations to come. There has to be a proper accounting for the resources expended, the hundreds of millions that are being expatriated and the thousands of jobs that have not gone to nationals.

Article Tools
Comments: 4
 

UsTrini39 Where the money?!

UsTrini39
Where the money?! I say again, where, O where, has all the money gone? This PM believes he can get away with anything! AND SO FAR HE HAS !!! Come on Trinidad and Tobago, WAKE UP! Or you may awaken some day to find Trinidad and Tobago down the river (in China or Malaysia) without a paddle!

Hi, I can contribute a few

Hi, I can contribute a few clarifications to the discussion.

1. To be best of my knowledge, the public Tennis Courts on the Prince's Building Ground and the Colonial Tennis Club were legally squatting on the plot of land, so while a temporary lack of Tennis Courts (until the construction of the King George V ones was complete) was regrettable, I don't think there is anything wrong with the state taking and that it owns and using it for a development project...

Besides I think the fact that the government spent almost 18 million on a new facility smacks neither of ignorance nor incompetence... I think here you clearly have an instance where the State realized the communal importance of the tennis facility and did its level best to give the people what they wanted... albeit in another location. You have to be a real cynic to see it any other way.

2. Yo always have to be careful with citing these planned completion dates... what matters particularly if you want to go after the guys at UDeCOTT is, when did they start construction, how long was construction scheduled to last and when was construction finished. At least that is the standard that is typically used and by that, the PM could go out and say it was finished on time... the delay stems from budget documents from 2006 or 2007 or whenever saying one thing and then reality (i.e. tennis courts in the way, etc.) making it a whole new issue.

Regardless from what I have heard within the industry (and I accept that there are many opinions on Chinese Labour) the Shanghai Construction guys did a great job in there. Not surprisingly though given their track record.

3. when we talk about budgets, all of us have to be MUCH more careful with numbers... there is too much apples and oranges going on in the public discourse... Two figures that always get mixed up are "Construction Cost" vs. "all-in cost". The Construction cost only covers the physical construction of a functional structure. the all in cost will include stuff like the relocation of the tennis courts, currency variation due to a declining US Dollar (remember the loan was issued in RMB) and most critically outfitting, i.e. furniture, computers for the class rooms, etc.
That's why you have all these different figures flying around... As far as the UDeCOTT guys are concerned, they fulfilled their mandate by constructing the building and holding the contractor to their original budget. As far as they are concerned, this was "on time" and "on budget".
If you are a government minister, your responsibility extends further. You have to provide a fully outfitted facility to UTT and Queens Hall, so the all in costs are going to be different.

I hope this answers a lot some of your questions.

Well Chester, I assume you

Well Chester, I assume you are in the Govt as your contribution is biased, now hang the jack!

lol, you're cute...

lol, you're cute...