Physical capital work on certain drainage projects start in the 2023 dry season and the highway from San Fernando to Point Fortin is targeted for completion in mid 2023.
And a final report on the collapse of the Mosquito Creek segment of the highway is expected in a couple weeks.
Works Minister Rohan Sinanan confirmed this at Monday’s meeting of Parliament’s Standing Finance Committee on the 2023 Budget
Sinanan was questioned by UNC MPs Roodal Moonilal, Dinesh Rambally, Dave Tancoo, Rushton Paray, Vandana Mohit, David Lee, Kadijah Ameen, Ravi Ratiram and Saddam Hosein on issues.
Sinanan said he was aware the main areas of concern are road and drainage works and the past month had demonstrated the continued impact on weather patterns, locally, regionally and internationally.
Sinanan added, “The ministry has taken the position of pursing an aggressive maintenance and upgrade programme while working with international partners to accelerate scope infrastructure interventions which has to cater for one in 100 year events as against one in 12- year events as may have been the case previously.”
He said in 2022 the ministry did 400-plus drainage projects.
He added that in some instances, especially under the Drainage Public Sector Investment Plan, rescoping and given the early start to the rainy season, would have seen the start of certain projects in the rainy season.
“To ensure proper implementation where this has occurred physical capital work has been scheduled for the start of the 2023 dry season,” he said.
The ministry has done 115 highway projects. Its 2023 priority projects included road upgrades, upgrade of pumps/gate inventory, continued implementation of its coastal programme, Port-of-Spain, East West corridor transportation projects with the Macoya Exchange, extension of Solomon Hochoy Highway to Point Fortin Highway, Grand Chemin Fishing Port and Diego Martin pedestrian bridge.
Indarsingh demanded fixing to be done in 24 hours of the “largest pothole in T&T’ in his area. He said teams have only come and looked, but nothing was done.
Sinanan assured a team would be sent yesterday (Monday) ,”Don’t worry, I know you’re a favourite in that area—I won’t have them laugh at you.” he said.
Sinanan said there was a $91 million allocation for road maintenance while repaving is done by contractors with smaller contractors for localised repairs. Underground cleaning has increased.
On Moonilal’s query about the collapse of the Mosquito Creek Highway segment, Sinanan said Nidco’s obtained a preliminary report and is now evaluating it and expects to send the final report to the ministry in the next couple weeks. A preliminary report has already been sent to the ministry.
Sinanan said Government had to be very careful of the process in revealing the report in case it had to take legal action against anybody .
“Once the official report is handed to the ministry, we’ll take it to Cabinet and with Cabinet’s approval it will be made public provided it doesn’t disadvantage anyone with whom legal action has to be taken if the report says that.”
Noting highway designs began in 2012, Sinanan added steps will be taken to ensure citizens were not disenfranchised and anyone who had to be held accountable would be.