Senior Reporter
jensen.lavende@guardian.co.tt
Joint Consultative Council (JCC) president Fazir Khan says the issue of cost overruns on government contracts is also a matter for the Office of the Procurement Regulator (OPR) to address.
He made the comment in the wake of the current controversy surrounding the ANR Robinson Airport development project in Tobago.
Last week, Opposition Leader Kamla Persad-Bissessar and Finance Minister Colm Imbert engaged in a public debate over the cost overruns on the project.
After initially indicating that the overruns were only $17 million, Imbert admitted to an error and adjusted the figure to $118 million in overruns.
The project, which was delayed by COVID-19 and land acquisition issues, was originally billed at $1.286 billion and increased to $1.7 billion. It is expected to be completed by June 2025.
Addressing the issue, Khan said while the contract was signed before the OPR received its legal authority, it does have some legal remit to review and report on all government contracts.
“The OPR has jurisdiction to investigate and review all ongoing government contracts under Section 13 (j) and report on them in their Annual Review under Section 24 of the said Act. I am still checking the OPR Annual Report issued in April 2024 to see what it reveals, if anything, about this China Railway contract,” Khan said.
“However, the public should be aware the country now has an independent body established in law, which has a mandate to not only investigate and report on such matters (like significant cost overruns on any State Contract), but should it find evidence of malfeasance, the OPR has the power under the new laws to bring punitive action to hold those accountable for misuse of public funds.”
Also addressing the issue, former Contractors Association president Mikey Joseph said the issue of cost overruns in the construction of the airport was a political nuisance, as most contracts have cost fluctuations depending on what is added or removed.
Asked about the increased costs, Joseph said: “This issue of cost overruns in any project is a political term. There is no way in any contract, or any system used for buildings, it talks about cost overruns. Only politicians talk that nonsense. When you have a project and you have a contract, you have specific terms and conditions and within that there are variations.”
Joseph said the cost overruns could have been due to the Government adjusting parts of the contract. He said with a design-build contract, for example, the changes by the government must come at a cost.
“If it is a design-build, then you have to assume that it is either the client’s brief that was insufficient and the client recognised he missed out certain things and it is now being included, or they recognised they want to improve or they want to change or increase the scope of works.”