It is now up to local contractors to finish the construction of the Port-of-Spain General Hospital’s Central block.
This, after the initial contractor, Shanghai Construction Group (Caribbean) Group Limited, pulled out of the project last Wednesday, citing challenges in continuing.
An approach similar to what was used to restore the Red House will now be used to complete the project. It will maximise local content and is expected to provide greater opportunity for local contractors and generate employment, the Urban Development Corporation of Trinidad and Tobago Limited (UDeCoTT) said yesterday in an update on the project.
The block was condemned due to its aged structure and damage from a 2018 earthquake. Prime Minister Dr Keith Rowley turned the sod for a new Central Block in November 2019. In January, however, Rowley confirmed work had stalled amid issues with SCG. The contractor had moved to terminate the contract last November.
In January, UDeCOTT confirmed the foundation and ground floor slab were completed and the erection of the structural aspects had commenced.
But yesterday, UDeCOTT detailed the situation leading to SCG’s final termination notice recently.
UDeCOTT stated, “A number of issues arose during the project, such as delays associated with the COVID-19 pandemic, supply chain issues and numerous, diverse claims by the contractor, SCG (Caribbean) Group Limited.”
By letter dated November 5, 2021, the SCG company issued a termination notice of its contract with UDeCOTT. The erection of steelwork halted shortly afterwards in November 2021, as the contract termination took effect on November 19, 2021.
UDeCOTT stated that several meetings were held with the contractor in an attempt to resolve the issues and proceed with the project.
While discussions were ongoing, UDeCOTT proceeded with work such as asbestos abatement and demolition of the existing Central Block and importation of the remaining steel. UDeCOTT has procured 65 per cent of the steel thus far.
“The (pandemic) lockdown in Shanghai has delayed the delivery of the remaining 35 per cent,” UDeCOTT said.
It added, “Despite the efforts, the contractor issued a letter dated April 8, 2022, citing a number of challenges in continuing the project, such as the continued lockdown in Shanghai, issues in relation to its staff and logistical issues it faced procuring materials. The contractor indicated that it believes it will be better for the T&T Government to find another contractor to complete the project. However, they are willing to support the project.”
As a result, UDeCOTT’s board, and subsequently the Cabinet, approved a new approach for completing the project.
The work will now be divided into seven packages and the tender for the first package will be issued next Tuesday. This includes completion of the superstructure, which encompasses completion of the remaining steelworks, shear walls and slab.
Other packages include builders’ work and mechanical, electrical and plumbing, medical equipment, furniture and ICT equipment.
UDeCOTT added, “This new approach would be beneficial, as works can commence almost immediately and be sequenced to cause no downtime. The tender process would provide the opportunity for specialised and general contractors to be awarded portions of the work and it would eliminate overheads by a main contractor. Of great importance, it would also maximise local content as it would provide greater opportunity for local contractors and generate employment. “
UDeCOTT noted, “This approach was successfully implemented with the Red House Restoration Project. The Red House was completed in record time and created hundreds of jobs.”
Assessment by UDeCOTT of all construction works at the Central Block will be completed and equipment will be installed by March 2024. Commissioning of equipment will be completed by mid-May 2024, allowing for subsequent project handover.