The Water and Sewerage Authority (WASA) has won its lawsuit against an insurance company over its refusal to release a $2.5 million performance bond for rehabilitation works on the San Fernando East Trunk Sewer after the contract for the project was terminated.
Delivering a judgment on Wednesday, High Court Judge Joan Charles upheld the State-owned utility’s claim against Bankers Insurance Company Limited.
The bond related to a contract for the project signed between WASA and Project Engineering Consultants Limited, based in Phoenix, Arizona, and La Romain-based Oilfield and Marine Sales and Services Limited.
Under the terms of the contract, valued at $25,452,552, the companies were given 180 days in which to complete the project and were required to provide a bond worth ten per cent of the contract sum.
While the contract was signed in September 2012, the bond was provided by the insurance company when it (the contract) was awarded after a tendering process several months before.
In June 2013, the engineering company assigned to the project wrote to the companies raising concerns over certain defects in their work.
It also complained that the companies had failed to present their proposed methodology for rectifying the defects and completing the contract.
In their reply, the companies indicated that their methods to perform their obligations had failed and they needed additional time to comply.
WASA refused their extension request due to their failure to submit their methodology.
WASA eventually terminated the contract based on the non-compliance and demanded the payment of the bond as under the contract it was entitled to $50,000 a day up to a maximum of the bond figure for delays in the project.
The insurance company refused as it claimed that the move was premature as the companies had to acknowledge their alleged breach or WASA needed to obtain a court order over it.
It also alleged that the project was delayed due to issues with financing and by specialist machinery that had to be imported.
It mainly claimed that the contract between the companies and WASA pre-dated the bond and was therefore void.
In upholding WASA’s case, Justice Charles rejected the insurance company’s claims.
Stating that it was aware that it had to provide the bond before the contract was signed, Justice Charles said, “In light of this, I conclude that at the time that the said performance bond was issued, the defendant was aware of the obligations of the contractor and agreed to act as surety in respect to the performance of these obligations.”
She also ruled that WASA followed the correct procedure for seeking the release of the bond.
As part of her decision, Justice Charles ordered the insurance company to pay 3.5 per cent interest on the bond between when WASA filed the case in 2015 to the date of the judgment.
WASA was represented by Neal Bisnath and Lydia Mendonca.