Curtis Williams
curtis.williams@guardian.co.tt
Could a decision by state-owned Petrotrin to change the royalty payment terms for A&V Oil and Gas cost the state-owned company hundreds of millions of dollars without it receiving a barrel of oil?
That is one of the issues that the arbitration panel is still to decide on, in the dispute between Petrotrin and A&V Oil over Petrotrin’s decision to stop A&V from operating its Catshill oil field in Rio Claro, based on allegations that A&V was claiming to be producing more oil than it really was and defrauding Petrotrin of significant sums of money.
The arbitral panel, which comprised Sir Dennis Byron, Lord David Hope and CVH Stollmeyer noted that A&V was required by the Incremental Production Sharing Contract (IPSC) to invest in improving oil production from the Catshill Field by, among other things, conducting a comprehensive survey of the field, working over existing wells using its production rigs, drilling new wells, using its drilling rigs and improving the infrastructure to facilitate increased production. The decision noted that in its submissions the A&V accepted that its production levels were low at the outset, and only began to increase from mid-2015 when new wells and work over existing wells started to produce returns from the investment.
It then turned its mind to increasing its investment with a view to carrying out a drilling programme of new wells to increase production.
On 18th April 2016 A&V wrote to Petrotrin seeking its commitment to renew the IPSC for a further 10 years to 2029. It explained that it expected to complete its work obligations by the end of that month with the drilling of its last commitment well. It had already offered to drill an additional 12 wells commencing in May 2016. At the end of that drilling programme, it would offer to drill up to 22 additional wells, making up a total of up to 40 wells drilled in the field. It said that an extension of the Contract was required to make that programme economic.
Guardian Media checked the records of the Ministry of Energy and Energy Industries and it showed that A&V drilled the most number of wells of any company in T&T in 2016 and 2017, but most of these wells were shallow and all were developmental drilling.
By letter dated 13th June 2016, in reply to the A&Vs’s letter of 18th April 2016 Petrotrin said that its Board of Directors had approved a series of revisions to the IPSC which altered the over-riding royalty rate, the base production rate and the first tranche crude oil rate provide for by Schedule C of the IPSC.
Although it did not commit itself to renewing the IPSC for a further 10 years as had been requested, the period of years set out for the revised base production rate and the first tranche crude oil rate extended for five years beyond the term of the Contract to the end of 2024.
It is this decision and what quickly followed that could end up costing Petrotrin tens of millions of dollars.
At a quarterly meeting on 16th June 2016, A&V informed Petrotrin of its plan to embark on an aggressive drilling programme. It reminded the Petrotrin of its request for a renewal of the term of the contract for another 10 years and asked for an urgent response to that request.
By Supplementary Agreement on the 18th July 2016, a series of revisions to the IPSC referred to in the Petrotrin letter of 13th June 2016 were agreed including a clause that, if the A&V had given written notice of its desire to renew the contract for a further term of five years prior to the expiry of its term, the parties would use their ‘best endeavours to negotiate in good faith the terms on an agreement for the renewed term’.
It is this that A&V is now relying on to say it had a legitimate expectation that the contract would have been renewed post-2019 and that it should be paid significant sums to recoup potential losses.
“The Claimant says that in reliance on that agreement it charged the Respondent on the basis of the changed royalty rates in its invoices, and it invested a substantial sum in drilling new wells to increase its production...The Claimant accepts in paragraph 374 of its Closing Submissions that the parties did not agree on a five-year extension to the IPSC when they executed Supplemental Agreement No.6. But it says that that agreement was not without effect when calculating future loss, as it provided in the new Article 3.3 that the parties would use reasonable commercial efforts to negotiate in good faith the terms and conditions for the renewed term following the Claimant’s notice of its desire to renew the IPSC. The question, it says in paragraph 379, is what could one reasonably expect to have happened had it given such notice? Its case is that it had a reasonable expectation that it would have been renewed for five years from 19th November 2019,” the Arbitral Panel noted.
For Petrotrin’s part, it is arguing that A&V had consistently failed to observe and perform the terms and conditions of the IPSC and, accordingly, that the conditions for renewal could not be met.
“That argument raises issues of fact to which the Claimant has had no opportunity to reply as it was introduced only in the Submissions in Reply, and which we cannot resolve without hearing further argument. Our decision on this issue must therefore be reserved for further consideration at the further hearing,” the panel said.
The A&V Oil and Gas issue first came to light when Opposition Leader Kamla Persad-Bissessar read on a political platform a report that alleged A&V Oil and Gas, which is owned by Nazim Baksh, a man Prime Minister Dr Keith Rowley describes as his friend, was charging Petrotrin for oil his company did not actually produce.
Petrotrin would subsequently investigate the issue and discontinue its contract with A&V drilling for crude from the Catshill field in Rio Claro.
The evidence before the tribunal also gave a look into some of the interactions that happened between personnel of A&V drilling and Petrotrin.
The decision noted, “As the Respondent points out in paragraph 170 of its Closing Submissions the evidence about any conversations between Mr. Baksh and Mr. (Visham) Ramnarinesingh fell well short of showing that there was an agreement to extend the IPSC. Furthermore, Article 45 of the IPSC [5344] provides that no modification or amendment of the Agreement shall be valid or binding unless provided in writing that specifically references the Agreement and that has been duly executed by an authorised representative of the parties. Irrespective of what may have been agreed to in conversations between the parties, no such agreement could take effect until the IPSC was amended in the way provided for by Article 45.”
Petrotrin’s attorneys are urging the company to take the matter to the High Court to prevent the state-owned company having to pay to A&V hundreds of millions of dollars.