The Estate Management and Business Development Company Ltd (EMBD) has lost its appeal over the decision of a judge to grant a summary judgment to Junior Sammy Contractors Ltd, over approximately $82 million in unpaid fees in relation to residential development in central Trinidad.
Delivering a written judgment yesterday, Chief Justice Ivor Archie and Appellate Judges Charmaine Pemberton and Ronnie Boodoosingh dismissed the appeal from the special purpose State company, which manages lands formerly owned by Caroni (1975) Ltd.
In the judgment, the appeal panel ruled that former High Court Judge Mira Dean-Armorer was not wrong to award the contractor a default judgment over EMBD’s inability to defend its case before being elevated to the Court of Appeal in 2020.
According to the evidence in the case, the legal dispute concerns a contract for the Caroni Savannah Residential Development undertaken by EMBD.
The contract was first awarded to another company in 2010 but was terminated after it (the company) failed to perform or complete the work.
Junior Sammy Contractors submitted a $231 million tender for the project and was awarded the contract to complete the development.
It sued EMBD after it only paid seven of the 13 interim payment certificates (IPCs), which were approved by the independent engineering company appointed by EMBD to act as its agent.
In its challenge over the contractor’s application for summary judgment, EMBD claimed that it could not pursue the action, as it had assigned the outstanding payments, which are the subject of the lawsuit, to ANSA Merchant Bank.
Justice Boodoosingh, who wrote the appeal panel’s judgment, stated that Justice Dean-Armorer was correct to rule that there was not an “absolute assignment”, as Junior Sammy Contractors retained the ability to take legal action over the debt-based agreement between the bank and itself.
He also noted that his colleague was not wrong to reject EMBD’s claim that the IPCs were inflated and the work was not completed as required under the contract.
Justice Boodoosingh agreed that the EMBD delayed mounting the challenges after the IPCs were issued by its engineer and the procedure under the contract was not followed.
“In other words, the contract provided a mechanism/process for a claim of this kind. That was not adhered to by EMBD,” he said.
He noted that such challenges to the IPCs could only be successful if the EMBD could prove fraud or defects in the work.
“Like the trial judge, after careful examination of the pleaded case, we find that there was not enough to support a proper pleading of fraud or abatement,” Justice Boodoosingh said.
As part of its decision in the case, the appeal panel ordered EMBD to pay two thirds of the legal costs incurred by Junior Sammy Contractors in defending the appeal.
The EMBD was represented by Jonathan Acton Davis, QC, Colin Kangaloo and Danielle Inglefield.
Ramesh Lawrence Maharaj, SC, Jagdeo Singh, Kiel Taklalsingh, Karina Singh and Shastine Motilal represented Junior Sammy Contractors.