The collapse of the South Trunk Road at Mosquito Creek has led to the loss of millions of taxpayers dollars, but this is not the only fallout as valuable fish spawning grounds are now in danger.
Bordering the edge of the Oropouche swamp and running parallel to the western coasts of the Gulf of Paria, the road upgrade was expected to solve the perennial flooding experienced by commuters for decades.
As part of the Solomon Hochoy Highway Extension project, this part of the highway dubbed Package 5 A required the most technical engineering and cost taxpayers more than $280 million.
But almost three years after the first two-kilometre lanes were opened, the newly constructed highway is now falling apart.
Under the Kamla Persad-Bissessar's People's Partnership administration, a causeway (a raised road or track across the low or wet ground) was proposed to safeguard the wetlands but this idea was shelved as it was deemed too expensive and would require another Certificate of Environmental Clearance.
The question now being asked is whether the causeway would have been the best option to protect the mangrove.
Speaking to Guardian Media, President of the South Oropouche Riverine Flood Action group Edward Moodie said the causeway would have been aesthetically pleasing and would have safeguarded plant and marine life.
"I was a consultant at NIDCO (National Infrastructure Development Company Limited) and they abandoned the idea of a causeway because it would have meant going back to the EMA for a CEC and they were afraid of (Wayne) Kublalsingh," Moodie said.
Consultant at the project under both the UNC and the PNM was American multinational engineering firm AECOM which boasts 100 years of engineering experience on its website. Halcrow Ltd was also part of the engineering and designs while Jusamco Pavers Limited, also known as Junior Sammy contractors executed the construction of the project according to the specified designs.
But Moodie, who did extensive research on the swamp, said it was only a matter of time before the entire area collapses.
He said because of the existing collapse, the project should be halted immediately until proper hydrological studies are done. He noted that an environmental impact assessment should be done as the project is having a devastating impact on the fish spawning grounds.
President of the South Oropouche Riverine Flood Action Group Edward Moodie, second from left, shows debris from the highway which clogged the river last year.
"There is a sandbank forming in the Gulf of Paria that is about 50 feet to 75 feet from where the highway is sinking. The pressure of gravel is pushing under and coming out in the softest area. We measured the crack on the walls and it is widening," Moodie said.
Highway debris clogs the watercourses
Many species of fishes including boshay and grantikai have not been able to spawn, Moodie added. The swamp, he said, is a breeding ground for 29 species of fish and numerous species of crustacean crabs, oysters, mammals, rodents, reptiles, amphibians and birds.
"The river is blocked up so the fishes cannot leave the sea to go upriver. They normally spawn in the mangrove roots which protect the fingerlings from predators. There are only two rivers that exit into the Gulf and the mouth of the Gordineau River is still blocked up after the construction of the bridge," Moodie said.
This was confirmed by Woodland fishermen who said they have to manoeuvre between rocks to prevent damage to their boat engines
Guardian Media visited the mangrove recently and saw evidence of highway debris littering the mangroves. Geotextile materials, coils of fabric and pieces of steel protruded from the sea, a dangerous trap to wildlife habitat.
Fishes, crustaceans and birds often get caught in the debris and die.
Even though the southbound carriageway remains open, taxi drivers said the area where the Gordineau Bridge is located has started to sink.
One of the cracks which widened along the Solomon Hochoy, Highway Extension project, Mosquito Creek.
KRISTIAN DE SILVA
"This area is holding up better than the northbound carriageway which is under construction and it is because under the UNC we piled mounds of materials to create an elevation and we waited for over 14 months for it to settle before we started to build," former works minister Suruj Rambachan revealed.
He noted that under his predecessor, a causeway was considered which would have been aesthetically pleasing and would have had no impact on the mangroves. However, Rambachan said this was not pursued as it was costly.
Rambachan could not provide any details of the proposed cost but noted that it was not impossible to build a road through marshlands as this was done in Florida and other parts of the world.
Ironically, despite engineering challenges and the impact on the nearby wetlands, Package 5 A was not opposed by Highway Reroute Movement's Dr Wayne Kublalsingh who fought the Mon Desir segment.
However, last week he said he was not surprised by the failure at Mosquito Creek as no proper hydrological study had been done before the project was executed.
He said "bogus hydraulics" was built "without understanding the hydrology and they have cost taxpayers billions of dollars."
Kublalsingh called on the Government to do a proper hydraulic system, bridges, culverts, embankments so they can have a proper flow of water from the river to the sea.
Sinanan waits for report
Minister of Works Rohan Sinanan said last week he was awaiting a report pending investigations into the cause of the collapse. The investigations are ongoing to determine what caused the failure.
"To minimise propagation of the failures, the earth fill and pavement loads on the embankment were immediately reduced. The situation is being monitored by surveyors three times daily to map the movement of the instability," Sinanan said.
He said the designers were doing a detailed review of geotechnical assumptions on the existing sites "to generate a relevant site-specific solution."
AECOM engineers declined to comment.
Last Sunday, Guardian Media exclusively reported the collapse of the sea revetment wall and the sinking of a 180-metre stretch of paved roadway. Since then, the entire area has been dug up and armed guards stationed at the site to prevent the media from capturing the further deterioration of the $280 million project.
History of the Solomon Hochoy Highway Extension
The first road across Mosquito Creek was built by Victorian engineers according to prominent researcher Glen Beadon. He said it was a two-mile ‘corduroy’ road (early log road or timber track-way) which was built in 1852 for "£1855 Sterling."
The decision to build the San Fernando to Point Fortin Highway was in the making for over 30 years. The National Physical Development Plan of 1984 included an alignment for such a highway inclusive of the development of Mosquito Creek. In 1998, a pre-feasibility study was done. A full feasibility study and initial designs were done by LEA-Trintoplan and Ecoengineering between 2005-2007. That final report indicated the 1998 study outlined the need for a more direct route between San Fernando and Point Fortin-La Brea. It highlighted traffic delays on sections of SS Erin Road from Cross Crossing to Siparia as well as traffic delays on the two-lane section of South Trunk Road and Southern Main Road, between Cross Crossings and St Mary’s Junction.
AECOM and Halcrow were consultants on the project and were in charge of engineering designs.
Mosquito Creek was said to be the most technical aspect of the highway. OAS Constructura failed to complete the road extension along the creek.
In June 2018, the Government announced that it will divide the project into packages to boost competition among local contractors and so drive down prices.
Jusamco Pavers Ltd and Namalco Construction Services Ltd tendered to complete Package Five. Jusamco's bids were 4.32 per cent and 2.4 per cent lower than Namalco's estimate, while Lutchmeesingh’s Transport Contractors Ltd, Sinohydro Corporation Ltd, and General Earth Movers Ltd’s offers were higher by 8.4 per cent, 15.51 per cent and 19.3 per cent respectively.
After evaluation Jusamco was determined to have offered the most economically advantageous price and was recommended for negotiations, following which a revised final bid of $280,976,489.08 VAT inclusive, some 6.54 per cent lower than the estimate, was submitted.