Kejan Haynes
WASA Chairman Ravindra Nanga has followed in the footsteps of Minister of Public Utilities Marvin Gonzales, praising the WASA workers who repaired the ruptured 48-inch pipeline last week, while also condemning those in traditional and social media who criticised, and in some cases spread misinformation about them.
“It is unfortunate that two of our daily newspapers opted to by-pass the facts and criticize all the faceless WASA workers who, in the face of unforeseen and unprecedented circumstances, did everything within their power, working through sleepless nights, to address the crisis and get water back into people’s homes as quickly as possible,” Nanga said in a letter sent to the media today. “Worse were the individuals who took to social media to deliberately spread misinformation and, in some cases, blatant falsehoods, all in an attempt to discredit WASA and the hard-working engineers and technicians, who were busily at work restoring the water for their very critics.”
Nanga said last week’s rupture was a lot worse than originally reported based in the preliminary assessment. Workers eventually discovered that a 48-inch concrete-encased steel pipe, which had been laid in the mid-1970s, had in fact imploded.
The WASA Chairman said officials worked hard to keep the public notified on the progress of the repairs through media conferences. He said looking forward, work has commenced on a long-term solution by installing 280ft of 48-inch steel transmission surge pipeline but there are more complications.
“During exploratory works, an extensive truss block supporting the concrete-encased steel pipe was discovered in the area of the Surge Tank,” he explained. “This has complicated the replacement process, and it is now necessary to re-route the new pipeline, as any work in the area of the truss block, risks rupturing the current pipeline and once again cutting off supply. WASA is taking all steps to avoid any new damage to the existing pipeline.”
He said WASA is currently mapping the new route to ensure that it is acceptable and excavation and fabrication works will commence shortly.
He expects work to take another two weeks but promises contingency measures have been put in place, in order to minimise further impact on the supply to customers.
Nango explained, once these repairs are completed, in the near future a second line, utilizing HDPE technology will be installed as a redundancy system, in order to ensure that this occurrence is not repeated.