The Government has informed the population that the Guaracara Refinery will restart, promising a significant economic boost and much-needed employment opportunities. No one doubts that restarting the Guaracara Refinery is technically possible. The critical question is whether the refinery can be managed and operated safely, reliably, profitably, and sustainably over its 15- to 20-year investment cycle across changing government administrations—without shifting massive financial risks onto Trinidad and Tobago’s taxpayers. This article aims to stimulate conversation and discussion on this important journey the country is about to embark on.
The foundation for moving forward
The Restart Committee’s assumptions and risks underpinning its findings of technical, commercial, and financial viability form the foundation on which the government is moving forward. The Restart Committee was led by former Energy Minister Kevin Ramnarine and included former Petrotrin vice president of finance, Shariba Ali Rajah; former vice president of retail and marketing, Kelvin Harnanan; former refinery manager, Gowtam Maharaj (now chairman of the Penal/Debe Regional Corporation and chairman of the Guaracara Refinery Board); UWI lecturer in engineering/maintenance, Kishore Jagroo; operations and process engineer, Leslie Chang; OWTU branch president, Christopher Jackman; electrical systems/former OWTU monthly representative, Danny Goolcharan; planning, economics, scheduling, and commercial port marine manager, Margaret De Silva Okando; Energy Ministry senior chemical engineer, Yashee Carrington; Energy Ministry chemical engineer, Anuskha Benny-Sookoo; and port, marine, and shipping expert, Len Chan Chow.
The committee’s report has never been made public, and the citizenry has not had the opportunity to critically review it. Furthermore, no one on this team has direct restart experience with refinery assets idled for over seven years at the time of the assessment. It remains unclear whether they engaged additional consulting expertise to assist with the techno-economic evaluation. Time will tell whether the Restart Committee emerges as the hero if all goes well, or the scapegoat if things go awry.
In the 2027 Budget presentation, Minister of Finance Davendranath Tancoo, said: “Our objective is to secure a credible, commercially viable and fully financed arrangement that protects the national interest while creating the conditions for renewed economic activity.”
Later, during the budget debate, the Honourable Minister of Energy and Energy Industries outlined his approach. Stripped of political jargon, Dr Roodal Moonilal’s plan breaks down into five main areas:
Legality first: The government is following a strict legal checklist to ensure political opponents cannot file immediate court injunctions to stop the restart once an announcement is made. They are also aiming to avoid repeating past irregularities flagged by the Office of Procurement Regulation.
Global interest: Investors from India, Africa, Europe, the Caribbean, and North America have expressed interest, driven by global fuel shortages and US energy security needs. The Government of Trinidad and Tobago (GORTT) is nearing the end of competitive bidding and is preparing to negotiate with a “preferred bidder or consortium.”
Protecting the state: To prevent a rushed, dangerous restart, the Minister noted a zero-tolerance stance on safety, warning against “blowing up Marabella.”
Fiscally, the state rejects using large sums of taxpayer money—citing a prior $95 million loss at NiQuan—and intends to shift all financial risk to private investors.
The local workforce: The state highlights our existing pool of local refinery experts as a primary advantage, implying the project can restart smoothly without relying heavily on expensive foreign labour.
The timeline: Instead of attempting to commission the entire refinery at once, the plan utilises a phased restart. Some product lines could be operational within six months after a deal is closed and regulatory approvals are cleared.
The missing piece: who is driving the bus?
While these high-level statements sound promising, the crucial details needed to reassure citizens remain closely guarded. We cannot expect political ministers to possess deep, technical knowledge of how to safely restart a complex oil refinery; that is the job of competent technical teams. Yet right now, those teams are invisible. Who are these teams, and what are their demonstrated accomplishments or experience in transactions of this nature? Who is leading and accountable for the RFP and Bid Evaluation process in the absence of an active Trinidad Petroleum Holdings Limited (TPHL) board?
To spark a meaningful national discussion and protect the public interest, the Ministry of Energy and Energy Industries should answer eight critical questions:
1) Who is on the evaluation team? Who is leading the restart process, and what are their qualifications? To build confidence, the public must know who is protecting our national interest, who to thank if it succeeds, and who to hold accountable if it fails.
2) Who drafted the Request for Proposals (RFP)? The RFP dictates exactly what investors are bidding on. Was it drafted by highly experienced commercial and technical subject matter experts?
3) Where does the bidding process stand? Has the formal RFP process been completed, or is the state still looking at a loose list of interested parties? Is GORTT preparing to negotiate with a preferred bidder or consortium in the absence of a transparent bidding and evaluation process?
4) Is there a preferred business model, and what is it? The union-backed company, Patriotic Energies and Technologies, has publicly stated it will play a key role. GORTT’s advocacy for a phased restart begs the question: who is investing—private entities, GORTT, or a joint venture—and what is the exact business model?
5) Can the Ministry of Energy police this project? Historically, the Ministry of Energy has lacked the staff and resources to properly oversee massive operations in its regulatory role. Does it currently possess the technical competencies required to ensure a safe restart?
6) Will environmental laws be enforced? Petrotrin historically maintained a poor environmental record. Will the new operator be strictly required to meet all EMA rules for air, water, noise, waste and secure a valid Certificate of Environmental Clearance (CEC)?
7) Is union representation guaranteed? Will the chosen investor be legally required to recognise the OWTU as the bargaining union for the refinery’s workers?
8) Do we truly possess the local expertise required to run the refinery? This must be evaluated against several historical realities:
* Petrotrin’s poor work culture previously reported by Shell Global, and poor performance reported by Solomon Associates;
* Petrotrin’s historical need to engage a former BP refinery manager and three direct expatriate reports to oversee senior plant operations, engineering, and maintenance in the years prior to the refinery’s closure;
* Petrotrin’s management record on its headline Gasoline Optimisation Project and the failed Ultra Low Sulphur Diesel plant;
* The NiQuan experience, which was marred by cost overruns, schedule slippage, a fatality, and loss-of-containment incidents; and
* The Limetree Bay Refinery disaster on St. Croix (US Virgin Islands). That facility faced major operational failures, toxic chemical releases, and severe environmental violations that forced an emergency shutdown in May 2021, leading to bankruptcy and multi-million-dollar class-action settlements after emitting dangerous levels of hydrogen sulfide, sulfur dioxide, and uncombusted hydrocarbons that contaminated local water cisterns and forced the closure of schools.
Reality check: The true roadmap to a restart
To help the public understand what a real refinery restart looks like, it is critical to outline the standard, multi-step engineering and commercial process required for an asset that has been sitting idle for nearly eight years:
Step 1: Selecting the Winner. A formal RFP is sent to qualified bidders. It remains unclear whether the current government utilised the bidding process completed by the previous administration or initiated its own. To date, no official winner has been announced;
Step 2: Deep-Dive Inspection (due diligence). Before committing capital, a serious investor must conduct a thorough rehabilitation study as part of a mandatory feasibility assessment. This study requires extensive visual testing of equipment and a rigorous review of maintenance records by experienced reliability experts. For an asset idled for eight years, this phase would take six to nine months and cost an estimated US$30 to US$45 million. This is based on an industry rule of thumb of 3 per cent of the total restart cost, which has ballooned to an estimated US$1 to US$1.5 billion—double or triple the initial 2019 estimate of US$500 million. (Notably, when the Restart Committee finished its work, Patriotic Energies engaged the Italian firm Tecnimont [MAIRE] to complete a rehabilitation study for US$50 million). Today, that expanded scope must encompass:
* Refurbishing all on-site process and utility equipment (pressure vessels, fired heaters, boilers, cooling towers, electrical, and instrumentation);
* Repairing offsite infrastructure, namely intermediate product tanks, pipelines, pipe supports, flare systems, and oily water separators;
* Reinstating terminal crude and product storage, berths, and marine loading facilities; and
* Executing necessary technological, regulatory, and environmental compliance upgrades.
Step 3: Ironing Out the Contracts. Finalising lease, purchase, and utility agreements (gas, water, electricity) typically takes at least two months after the inspection phase. If a consortium is involved, navigating complex joint venture agreements can stretch this timeline significantly before reaching an executable agreement.
Step 4: Repairs and Restoration. Physical rehabilitation takes substantial time. Even under an optimistic, phased approach—such as restarting the refinery in a simple hydro-skimming mode before activating more complex, profitable processing units—it will take more than six months of intense engineering work to guarantee a safe, incident-free startup.
Realistically, after a preferred bidder is engaged, it will take 14 to 17 months just to produce basic products in a simple mode of operation. Given the massive remediation work needed for mechanical and electrical systems left idle for close to eight years, it is highly probable that it will take at least 17 months before the refinery produces anything at all.
Why Government-led projects fail
Ambitious megaprojects—especially those driven by states around the world—frequently collapse or fail to deliver due to four structural pitfalls:
* Lack of long-term vision: Projects are often launched without a clear, strategic purpose, failing to align with actual national priorities;
* Unrealistic design and political timelines: Initiatives begin without rigorous feasibility studies. Instead, political decisions rush them forward, prioritising short-term voter appeal over long-term commercial sustainability;
* Weak institutions and political shifts: Fragile governance structures and shifting political interests disrupt progress. Projects are too often approved to reward specific interest groups rather than to advance national development; and
Corruption and mismanagement: Financial weak spots—ranging from inflated contracts to misallocated funds—thrive under poor oversight. This lack of accountability leads to stalled projects, ballooning budgets, and operational chaos.