BPTT has suffered another major setback as its long awaited Cassia C project has been further delayed and will not come on stream until the end of the year.
Cassia C is expected to deliver over a quarter billion standard cubic feet of low pressure natural gas and is now to be delayed by more than a year according to highly placed sources at the company.
In an emailed response, BPTT confirmed the further project delay, saying COVID-19 was responsible for its inability to deliver the natural gas on time.
BPTT told the Business Guardian, “The hook up and commissioning phase of the Cassia C project is continuing and first gas is expected in the second half of the year. The project was initially planned to come online in 2021 but delivery was pushed to 2022 due to the impact of COVID-19.”
The company’s failure to deliver on its Cassia C project and its failed infill drilling programme have significantly hurt the country’s natural gas production and government revenue.
It has also negatively impacted everything from LNG output to the gas available to the petrochemical sector.
The lack of natural gas from BPTT has also been the cause for the decision to shut the Train 1 LNG plant as the National Gas Company Ltd (NGC) wasted more than a quarter billion dollars behind Train 1, hoping it would have access to more gas that was not forthcoming.
BPTT has also not been able to meet its contracted obligations and has been shorting both Atlantic LNG and the NGC of natural gas.
However under its contracted agreement NGC has no recourse for BPTT’s failure to provide it with contracted quantities although the NGC was forced to pay out huge sums to downstream companies for its failure to provide them with all the contracted quantities of natural gas.
1) Can BPTT say whether its Cassia project has been delayed again to the end of the year?
2) If so what are the reasons for the delay?
3) How long has been the delay from the original start up timeline to the latest estimated start up date?
4) How has this impacted BPTT’s ability to deliver gas to its customers?
5) What is expected to be the sustained production of Cassia when it gets going?
BPTT said, “Cassia C will deliver between 200-300 million standard cubic feet of gas a day (mmscf/d) and production will be put towards fulfilling our existing contractual obligations.”
Statistics from the Ministry of Energy and Energy Industries clearly demonstrate the deleterious impact on the country’s gas supply that BPTT has been having over the last twelve years.
In 2010 when all the companies were getting all the gas they needed, T&T’s average production was 4.33 billion standard cubic feet per day (bscf/d), of which BPTT produced on average 2.565 bscf/d. Fast forward to 2018 and you would find BPTT’s production fell to an average of 2.0 bscf/d, or by 500 million standard feet per day (mmscf/d), the result was that T&T’s total natural gas production fell by 700 mmscf/d.
In 2019 BPTT’s production dipped slightly to 1.9 bscf/d, so too did the country’s production which fell slightly to 3.588 bsc/d. But by last year BPTT’s production plummeted to 1.244 bscf/d and the country’s overall production crashed to 2.579 bscf/d, a 1 bscf/d fall, of which BPTT was responsible for 70 percent of that drop off.
Only recently BPTT confirmed that this year it will produce a mere 1.25 bscf/d, 750 mmscf/d less than it had produced on average in 2018.
The figure is also significantly less than it told the Ministry of Energy in July last year when it said that it would produce 17 per cent less than originally forecast in 2020 and even that was down by 15 per cent from its prediction in 2019.
In a confidential series of documents which the Business Guardian obtained, BPTT told the Dr Keith Rowley administration that going forward it should expect much lower than forecast natural gas production, with the shortfall being 15 per cent in 2021 and over ten per cent until 2024.
The documents showed that even that the Matapal and Cassia C projects that were expected to increase production by about 140 (mmscf/d), this is not going to be the case.
The news effectively put to an end any thoughts that T&T could even average 3bscf/d in 2022, a figure it was able to reach at the start of 2021, before the precipitous falloff in BPTT’s production.
The news could not be worse for Finance Minister Colm Imbert who should have been smiling these days with high commodity prices, but low production has meant a major opportunity lost for additional revenue and in particular the earning of scarce foreign exchange.
In response to questions from the Business Guardian, BPTT said it ended 2021 averaging 1,250 mmscf/d.
BPTT said, “We expect production for 2022 to be within the same range.”
The company blamed technical issues for the precipitous decline in production in 2021 and it admitted that even the coming on stream of its Cassia C project will only hold production in place.
“During 2021 we experienced accelerated production decline due to technical issues, which was partially offset when we brought Matapal onto production in September. For 2022, production levels will be supported by gas from Matapal, and the Cassia C development which is planned to come online in 3Q 2022.”
According to the latest figures from the Ministry of Energy and Energy Industries for the first 11 months of 2021 natural gas production averaged 2.578 bscf/d with the production of 2.385 bscf/d in November compared to 3.001 bscf/d in January.
BPTT said it will continue to invest in efforts to grow production. It pointed to the sanctioning of its joint project with EOG Resources, it also points to the return to infill drilling as examples of its efforts to improve production.
“As we continue to invest in production generating activities in Trinidad, we were pleased to sanction the EOG Operated Mento development at the end of last year, the BHP Operated Calypso development completed appraisal well and BPTT plans to restart our infill drilling programme later this year. We are also working on a number of future development options for BPTT, including our next major project the Cypre development which we are hoping to sanction this year,” BPTT said.
On the petrochemical side where prices are high and the returns best for the Government, the industry continues to suffer from natural gas curtailment.
The Ministry of Energy figures show ammonia production for the first 11 months of last year totalling 4,481,698, below the 5.2 million metric tonnes capacity.
Its methanol productions was 5.035 million metric tonnes.
With Train 1 dead T&T’s installed LNG capacity is under 2 bscf/d, for the first 12 months the average production was a mere 1.256 bscf/d.
All of this points to continued challenges for government and the economy.