The National Gas Company (NGC) has told Touchstone Exploration that it expects to be ready to receive first gas from the Cascadura natural gas and associated liquids facility by the end of June.
According to a release from Touchstone the company was notified on February 24 by NGC that they expect to be ready to receive first gas from Cascadura on or about June 30.
“Touchstone remains on track to complete the Cascadura facility prior to this date to ensure production can commence as soon as NGC is in a position to receive first gas,” the release stated.
Touchstone’s president and chief executive officer Paul Baay said, “We are encouraged to have received an expected first gas date from NGC. Although this is later than we were anticipating, we can now plan the final phase of our various work streams to minimise costs and optimise services.”
“First gas from Cascadura will be a transformative achievement for Touchstone, and we thank shareholders for their continued support and patience as we work towards this significant milestone,” Baay said.
He added that Touchstone expects that the funds raised late last year and its current base production will allow the company to complete drilling the Royston-1X well and prepare its next development locations at Cascadura while it finalises construction of the Cascadura facility.
The release also outlined the approximate construction status of the Cascadura facility.
It noted that the civil and concrete foundation work for the main process facility equipment is complete; the flare stack is procured, with the associated foundation work commencing imminently; the communication tower is approximately 80 per cent complete; the pipe racks are approximately 90 per cent assembled with hydrotesting initiated, and the units are expected to arrive at the facility within the next three weeks.
Additionally, it detailed that the on-site condensate tanks are approximately 65 per cent complete; the compressors, separators, and vapour recovery units have been safely transported to the facility; and all process equipment for the facility has been acquired.
Touchstone Exploration is a Calgary, Alberta-based company engaged in the business of acquiring interests in petroleum and natural gas rights and the exploration, development, production and sale of petroleum and natural gas.
Touchstone is currently active in onshore properties located T&T.