Lead Editor, Newsgathering
chester.sambrano@guardian.co.tt
Former Community-based Environmental Protection and Enhancement Programme contractor Eastman Enterprises Ltd has suffered another legal blow after it was ordered to pay the company’s legal costs after the conclusion of an appeal on the use of an Alternative Dispute Resolution clause in both parties’ contract.
A statement issued by CEPEP yesterday about the legal matter stated that the Appeal Court panel found that the contractor was wrong to bypass the clause by filing a claim in court.
It said the parties had agreed to use dispute resolution before approaching the courts, and bypassing that process removed the purpose of the agreed procedure.
The ruling came weeks after Eastman Enterprises Ltd failed in its bid to revive its lawsuit challenging a mass termination exercise at the State company. The company’s appeal was dismissed after it challenged the decision by a judge to stay the case based on its failure to engage in mediation and arbitration before litigation. In the November 20 matter, the Appeal Court panel of judges found that High Court Judge Margaret Mohammed could not be faulted for staying the case based on Eastman’s conduct after its contract and those of over 300 fellow contractors were terminated based on a Government directive at the end of June.
But the panel also ruled that Justice Mohammed wrongly referred preliminary contentious allegations over the mass renewal of contractors days before the general election in late April to the Office of the Director of Public Prosecutions (DPP).
In the latest ruling, the statement from CEPEP stated that Senior Counsel Larry Lalla, who appeared for the contractor with attorneys Kareem Marcelle and St Clair Michael O’Neil, argued that the court should make no order as to costs.
Lalla submitted that each party should bear its own costs because the Court of Appeal ruled that the trial judge erred when she referred the matter to the Director of Public Prosecutions.
The court rejected the argument in a unanimous judgment by Justices Peter Rajkumar, James Aboud and Ricky Rahim.
It accepted CEPEP’s position that the referral issue formed a minor part of the appeal and did not justify altering the original costs order.
The panel found the main issue was about how the Alternative Dispute Resolution clauses operate as a condition precedent to litigation.
The court said the referral to the DPP was not a significant aspect of the appeal and did not occupy any real time during the hearing.
It held that the issue did not affect the main bases of the stay application or the issues determined by both the trial judge and the appellate court.
The court ordered the losing party to pay CEPEP two-thirds of its legal costs, subject to a 20 per cent discount to reflect the reversal of the DPP referral.
CEPEP, in its statement, also urged contractors to follow their contractual terms and said it remains committed to the rule of law.
Eastman Enterprises first took court action in early July after the mass dismissal of contractors and workers from CEPEP. The legal action was followed by an appeal in August.
