The Estate Management and Business Development Company (EMBD) has been ordered to pay over $427 million in unpaid fees to a mega-contractor from La Brea, for infrastructure works it performed on four residential communities for former Caroni (1975) Limited.
Although Namalco Construction Services was seeking over $1.3 billion through its lawsuit against the State-owned special purpose company, High Court Judge Ricky Rahim ordered less than half the claimed amount, as he partially upheld EMBD’s defence and counter-claim over an alleged “conspiracy” between the contractor and a former senior EMBD official.
In the lawsuit, filed in 2016, Namalco was seeking compensation for its unpaid contracts for infrastructure works at projects at Cedar Hill, Roopsingh Road, Petit Morne and Picton Monkey Town.
In defence of the claim, EMBD contended the company’s invoices were inflated and the work did not meet requirements set by EMBD. EMBD also alleged several supplemental contracts for the projects awarded by its former CEO Seebalack Singh should be voided, as he (Singh) did not have the remit to approve such without a tender process.
Namalco was initially seeking payment for six contracts but two were split from the case, as they fell under a separate $200 million lawsuit brought by the Government against it and four other contractors.
In that claim, EMBD is alleging the contractors conspired with the company’s former officials to obtain contracts in September 2015.
Oropouche East MP Dr Roodal Moonilal, former EMBD CEO Gary Parmassar and former divisional managers Madhoo Balroop and Andrew Walker are listed as parties in that claim, which is yet to go on trial before Justice Frank Seepersad, who inherited the case after Justice James Aboud was elevated to the Court of Appeal.
In the 245-page judgement, Justice Rahim ruled the court had the power to consider challenges to the validity of Interim Payment Certificates (IPCs) sent by Namalco for payments to be made based on abatement or diminution in value. However, he ruled the IPCs under the original agreements could not be faulted by EMBD because Namalco did not provide sufficient documentation to buttress its claims.
Justice Rahim also ruled that decisions on the initial agreements made by the Dispute Adjudication Board (DAB), appointed by both parties, were binding, conclusive and incapable of being the foundation of EMBD’s legal challenge.
Despite finding that EMBD was liable for its remaining balances on the initial contracts, Justice Rahim invalidated the supplemental agreements which raised the Roopsingh Road and Petit Morne projects by approximately $185 million and $129 million respectively.
While Justice Rahim ruled that Singh breached his fiduciary duty by approving the substantial contracts when he only had the clearance to approve contracts under $1 million, he noted the issue was cured by the fact that EMBD’s board subsequently approved them.
However, Justice Rahim said the agreements had to be voided, as the evidence in the case showed Singh and Namalco were engaged in an “unlawful means conspiracy” to inflate the contracts.
“No other intention is apparent on the evidence and this remains the sole reasonable inference of intention to be drawn having regard to the fact that the sums claimed have since been shown to be much more than that which obtained under the original award and which would have been reasonably claimable for new work even at new prices as set out,” Justice Rahim said.
“This issue has been scrutinised by this court and has caused much disquiet as there appears on the evidence to be a lurking suspicion of agreement,” Rahim added, as he noted neither Singh nor Namalco’s CEO Naeem Ali testified before him.
As part of the lawsuit, EMBD brought an ancillary claim against its project engineers who certified the projects - Walker, Atlantic Project Consultants Limited, BBFL Civil Limited and Lee Young and Partners. It claimed the group should be made to pay a portion of the compensation if it was eventually found liable, as they were allegedly responsible for the IPCs that were upheld through negligence.
While Justice Rahim ruled there were some breaches of duty on the part of the four engineers, he ruled they could not be ordered to indemnify EMBD, as it (EMBD) suffered no loss.
The claim against Walker was stayed pending the ongoing legal proceedings before Justice Seepersad, while the case against BBFL was also stayed for EMBD to provide additional submissions based on Justice Rahim’s findings on the alleged conspiracy.
The cases against Atlantic and Lee Young were dismissed with EMBD being ordered to pay the former $1.6 million in outstanding fees for one project and their fees for the three other projects being assessed by a High Court Master at a later date.