The Government said that a Tier 4 data centre, which first began under the former administration, is not yet complete even as it moves ahead with proposals for two new data centres with Artificial Intelligence (AI) mining capabilities.
A data centre is a centralised physical facility packed with servers, storage drives and networking gear that acts as a massive digital warehouse, storing, processing and distributing data, hosting everything from cloud applications to websites. On the other hand, an AI data centre (sometimes called an AI factory) is a highly specialised facility purpose-built to train and run artificial intelligence and machine learning models.
The data centre under construction is a Tier 4 data centre for the former government’s digitalisation expansion for the period 2024–2027. As it stands, T&T already has five data centres—Fujitsu, TSTT, Digicel, Cable and Wireless, and Air Link—which are classified as Tier 3 data centres.
Guardian Media was told that “some of the electronic gear for that data centre arrived and was put to use in TSTT’s data centre to be moved when the Tier 4 facility was completed.”
On Sunday, Guardian Media reported that a Tier 4 data centre project began in 2022 under the former administration and was to be located at the Phoenix Park Industrial Estate. That initial tender had also included a solar park capable of producing 500 kilowatts of electricity and stipulated that the data centre should be “at a minimum Tier 3 certification at the point of commissioning if the elements for Tier 4 are not available within the timeline specified.”
It was funded by a US$120 million loan from CAF – Development Bank of Latin America and the Caribbean – and was undertaken through the Ministry of Digitalization, now the Ministry of Public Administration and Artificial Intelligence (MPAAI).
“Tier 4 data centres provide the highest levels of infrastructure redundancy, fault tolerance and availability. Importantly though, the Tier differences have nothing to do with scale; you can have a small Tier 4 facility,” an informed source explained.
“The Tier 4 data centre currently under construction is intended to support key government mission-critical operations, not dedicated AI mining. AI mining workloads typically have much higher and more consistent power consumption than government mission-critical systems. In addition, the users of government mission-critical services are primarily domestic, making local infrastructure especially important. By contrast, AI mining generally serves offshore customers and therefore depends more heavily on international fibre connectivity than on domestic infrastructure,” the source explained.
Ministry’s statement
According to a statement from MPAAI, “the former PNM government proposed a Tier IV National Data Centre at Phoenix Park Industrial Estate to support Government digital services, strengthen national cybersecurity and reduce the State’s reliance on costly external data hosting arrangements. Despite those plans, the project was never completed or operationalised by the former administration.”
“A Tier IV National Data Centre is designed to provide secure Government data storage and digital services. Its Tier IV classification refers only to the reliability and resilience of the facility; it is not a measure of artificial intelligence capability,” the statement said.
Guardian Media understands that the holdback was civil works being managed by another state company.
In December 2025, according to procurement notices by the MPAAI, the Government sole-selected and leased land for 20 years for the data centre.
In an additional notice, it sole-selected a contractor to conduct civil works for the data centre, which were to be completed last month (June), with a 10-day standstill period.
It also procured rated engines, equipment, operations staff, janitorial services, security services and preventative maintenance services for one-year periods.
The statement did not disclose who the contracts were awarded to or whether the location was still at the industrial park, as it is not listed among the estate’s tenants. Guardian Media had reported that the location of the data centre has not been disclosed by the Government, nor whether it has established agreements with the country’s utilities.
Instead, on July 10, the Government of T&T signed three MOUs, two of them for the proposed establishment of large-scale data centres and artificial intelligence (AI) infrastructure—one with Ernst & Young (EY) LLP to partner with third parties on a 300-megawatt data centre and another with Hummingbird AI Holdings for a proposed 150-megawatt centre with the ability to scale up to 500 megawatts.
“Procurement is not proof that a facility has been completed or commissioned, and an MOU is not a construction contract or final investment approval,” the ministry’s statement said.
The ministry’s statement noted that the AI facilities contemplated under the Government’s Memoranda of Understanding with Ernst & Young LLP and Hummingbird AI Holdings are proposed commercial, high-performance computing facilities intended to support enterprise AI and other advanced computing applications.
“They involve a completely different technical architecture, investment model and purpose,” the statement said.
The Government’s data centre, as well as the proposed Hummingbird and EY centres, would be classified as Tier 4.
An industry source raised concern about the Government signing MOUs with companies rather than a country, for instance the United States. He noted that under the country’s procurement regulations, if the project advances, it will have to fall under the Office of Procurement Regulation.