The National Infrastructure Development Company Limited (Nidco) will have to wait until December 14 to learn the fate of its lawsuit seeking to set aside the over $850 million arbitration award over the Solomon Hochoy Highway extension project.
High Court Judge Frank Seepersad set the date to deliver his judgment in the case after hearing submissions from attorneys representing Nidco and Brazilian construction firm Constructora OAS SA during a hybrid hearing in the San Fernando High Court on Friday..
Presenting submissions on behalf of Nidco, British King’s Counsel Anneliese Day claimed that the award issued by three arbitrators from the London Court of International Arbitration in April should be set aside as the panel made numerous errors when assessing the case.
She pointed to several instances in which she claimed the panel failed to provide reasons why it ignored evidence, which supported Nidco’s contentions.
Responding to the submissions, OAS’s lawyer Rolston Nelson claimed that Seepersad should not entertain the case based on a clause in the contract between the parties, which stated that they would resolve their disputes solely through the arbitration process.
“This is a consensual process where the parties choose their judges. The court merely supervises to ensure that there is no bias,” he said, as he noted that the panel selected by the parties was very experienced.
He also pointed out that the clause was included in the contract by mutual consent and was intended to ensure that there was a mechanism to quickly resolve disputes between the parties to avoid lengthy and costly litigation before the local courts.
“One has to give deference to what the tribunal found,” he said.
Day suggested that the clause should not be strictly applied based on the public interest in the case as taxpayers would have to pay the compensation ordered for OAS.
“We are not seeking to appeal. We want the award set aside and remitted to the tribunal,” she said.
“Even the most eminent practitioners can make errors and this is exactly what happened,” Day said.
She also stated that the arbitration panel did not correctly decide that it was entitled to terminate the contract as OAS was under judicial restructuring due to insolvency.
“It was a bizarre and unsupported finding that OAS had not abandoned the works when it had,” Day said.
Nelson responded by stating that the company’s precarious financial situation was partially due to Nidco’s failure to make interim payments as required. He also suggested that his client only began to demobilise work on the project after it began talks with Nidco over the amicable termination of the contract.
In early 2011, OAS was awarded the contract for the project, which was then estimated to cost approximately $5.3 billion.
After the contract was terminated, the project was put on hold for several years before being restarted with local contractors.
In August, last year, Nidco announced that the project was three-quarters complete.
However, several months later a segment of the highway at Mosquito Creek collapsed.
Delivering a decision on a partial final award on April 16, arbitrators John Fellas, Adam Constable, KC, and Andrew White, KC, upheld OAS’s arbitration claim against Nidco and ordered US$126.3 million in compensation.
In the 223-page ruling, the arbitration panel ruled that Nidco was wrong to have terminated the contract based on the two main grounds it claimed.
In the arbitration proceedings, Nidco claimed that Constructora OAS effectively abandoned the project in late 2015 after it slowed down work, dismissed most of its staff and became insolvent by letting debt accumulate to suppliers and contracts.
The company denied any wrongdoing as it claimed that the issues raised by Nidco were due to the fact that it (Nidco) failed to make a major interim payment under the contract.
It claimed that at the time of the termination, it had injected a further US$31million in the project and had renewed its performance and retention bonds.
In upholding OAS’ case, the arbitration tribunal ordered that it be paid US$127,072,326 in damages minus the US$706,426.70 offset granted to Nidco.
The damages represent the company’s claims for performance and retention securities, a series of unpaid interim payment certificates (IPCs), materials in stock, temporary works, and contracting equipment.
The compensation to be paid to the company can still rise as the arbitration panel requested further submissions from the parties on whether the damages awarded could attract interest.
The tribunal also has to consider the company’s claim for additional damages on the ground that Nidco was overpaid when it seized the bonds in connection with the advance payment deductions.
In July 2019, Cabinet announced a Commission of Enquiry to investigate aspects of the project including whether a ministerial oversight committee under the former People’s Partnership government had fulfilled its mandate.
The committee was headed by former prime minister and current Opposition Leader Kamla Persad-Bissessar and included several former members of her Cabinet.
The commission, which is yet to commence its work, is to be chaired by retired judge Sebastian Ventour, with attorney Gregory Delzin serving as commissioner.
Nidco was also represented by Jason Mootoo.