Works and Infrastructure Minister Jearlean John has defended a $33 million reduction in funding for contracted highway works in the 2027 Budget compared with the original 2026 allocation, saying the ministry can contain costs by using its own workers.
“Nobody can say we are missing in action. We’ve been doing a lot of work,” John said during the Standing Finance Committee’s examination of Budget 2027.
Her defence followed repeated Opposition questions about whether the ministry could adequately repair roads, patch potholes and address landslips with reduced funding, limited supplies and an ageing vehicle fleet.
The Highways Division has been allocated $47 million for “Other Contracted Services” in 2027, compared with an original allocation of $80 million in 2026. That is a reduction of $33 million, or 41.25 per cent. However, the proposed allocation is about $504,000 more than the revised 2026 estimate of $46.5 million.
John said the item covers landslip repairs, slope stabilisation, drainage works, geotechnical investigations, crossing reconstruction, traffic management, guardrail installation and asphaltic materials for road patching.
Asked why the original 2026 allocation had been reduced, she said the ministry was increasingly relying on its employees.
“A lot of it is because we are doing quite a lot of the work in-house, so we don’t have a markup,” she said.
John cited a crossing repair for which a tender had exceeded $3 million, saying ministry staff had completed the work successfully.
“The staff of the ministry did this piece of work splendidly,” she said.
She also pointed to work at Las Lomas, describing it as technically challenging and praising the employees involved.
“These are highly skilled, highly trained people, very enthusiastic people,” she said.
The Opposition questioned whether the explanation matched the resources available.
“Can you explain, therefore, why the allocation for materials and supplies, which is what your in-house workers would use, was just about $1 million?” Opposition MP Colm Imbert asked.
Imbert later identified the precise 2027 provision for highways materials and supplies as $1.5 million.
John maintained that additional funding was available elsewhere.
“We have an item which you’ll find eventually in the Consolidated Fund for $15 million,” she said.
Opposition MPs also questioned whether the ministry’s vehicles and equipment could support the additional work.
“With your old, broken-down fleet, your minuscule allocation for materials and supplies, you believe you can replace this $34 million that you were not given by the Minister of Finance?” Imbert asked.
John acknowledged that some vehicles were more than 20 or 30 years old. She said the ministry was working to improve its capacity to repair them and obtain spare parts, and that funding would also allow it to purchase some replacement vehicles.
Asked again whether she was satisfied with the reduced provision, John pointed to projects completed the previous year.
“Because last year, we spent $44 million with 48 projects, and I can stand up here all day now, if you wish, and I can call out all of the projects,” she said.
She cited landslip repairs, road rehabilitation and geotechnical investigations among the works undertaken.
“We’ve been patching everywhere,” John added.
She said collaboration with WASA was helping to address technically difficult road failures, which required more time and intervention.
“Together, we are getting these things under control,” she said.
John also pointed to efforts to restore the Agua Santa plant, saying it was close to becoming operational.