Senior Reporter
kevon.felmine@guardian
Residents in several communities have complained of discoloured water and supply problems in recent days.
Guardian Media received complaints from residents in Santa Cruz, Mt Hope and St James.
Yesterday, the Water and Sewerage Authority (WASA) said it was flushing affected areas to clear temporary discolouration following a scheduled maintenance shutdown at the Desalination Company of Trinidad and Tobago (Desalcott).
WASA said temporary adjustments were made to the water transmission system during the shutdown. As the system returned to normal operations and water pressure was restored, some customers experienced discoloured water.
The authority assured customers that the water remained safe for domestic use. It advised those experiencing discolouration to run their taps for a few minutes to flush their internal plumbing systems and apologised for the inconvenience.
Meanwhile, some WASA customers face a longer wait for water after the restart of Desalcott’s desalination plant was delayed until Thursday. Residents have complained that water has not reached their taps even on scheduled supply days.
Public Utilities Minister Barry Padarath said yesterday that Desalcott, which was due to resume operations on Sunday after its annual maintenance shutdown, encountered mechanical problems. He said WASA’s acting chief executive officer had told him the plant was now expected to resume operations by Thursday.
“I spoke with the acting CEO of WASA on my way here this morning. He advised me that today is Tuesday and that, by the latest, Desalcott is expected to resume operations on Thursday,” Padarath said.
WASA had advised customers that Desalcott’s annual maintenance shutdown would run from September 28 to October 4. The Point Lisas plant supplies WASA with about 40 million gallons of water daily, supports the Point Lisas Industrial Estate and augments supplies to parts of central and south-west Trinidad.
WASA had said water deliveries were expected to resume from noon on October 4, with the full contracted supply expected within 24 to 48 hours.
Padarath said the annual maintenance was planned, but Desalcott encountered problems during the work.
“They had some unforeseen circumstances,” he said. “This is an annual maintenance exercise. We usually try to get the work done before the hectic periods of Divali, Christmas, etc. They had some mechanical issues at their facility, which created delays, but they have assured us that we will be back up, looking at Thursday of this week.”
The delay has added pressure to a water system already facing production constraints.
Padarath said heavy rainfall had increased the amount of sludge in reservoirs supplying the Caroni Water Treatment Plant, requiring desilting work that was almost complete.
He also said all of WASA’s dams were below 70 per cent capacity, with some in the 50s.
“Those dam levels have created significant challenges for us because it is not an issue of distribution; it is an issue of production,” he said.
WASA is trying to offset reduced production by bringing in additional water from Desalcott, wells and other sources. However, some residents have complained that they received no pipe-borne water despite their communities being listed on WASA’s temporary supply schedules during the shutdown.
Padarath acknowledged that WASA had not always been able to maintain the schedules, but said the problem was not uniform across the country.
“You are speaking of all of Trinidad and Tobago without providing me with any specifics, because what we usually do is get the data from the different regions,” he said. “So far, the only region that is creating a challenge at this point has been the eastern region.”
He said reduced production, partly caused by low dam levels, had affected WASA’s ability to maintain the schedules.
Padarath said the authority had also redeployed water trucks, particularly to the eastern and north-western regions, while tank farms in parts of south Trinidad were operating at full capacity. Tank farms in Penal, Debe, Oropouche, Fyzabad, Siparia and Princes Town were serving at least 600 households a week, with turnaround times of about two to three hours, he said.
The Government is also exploring additional tank-farm capacity in Cumuto, Manzanilla, Toco, Sangre Grande and other areas.