Brazilian construction firm Constructora OAS SA will have to wait to learn the fate of its appeal over a judge’s decision to set aside its almost $850 million arbitration award in relation to the Solomon Hochoy Highway extension project to Point Fortin.
Appellate Judges Nolan Bereaux, Mark Mohammed and Peter Rajkumar reserved their decision on the appeal after hearing extension submissions from lawyers for the Brazilian company and the National Infrastructure Development Company Limited (Nidco) at the Hall of Justice in Port-of-Spain yesterday afternoon.
In the appeal, the company is contending that High Court Judge Frank Seepersad was wrong to have set aside the arbitration award and remit the case to the London Court of International Arbitration (LCIA) for its reconsideration in mid-December 2022.
Presenting submissions, OAS’s lawyer Rolston Nelson, SC, claimed that neither Justice Seepersad nor the Court of Appeal had the jurisdiction to review the LCIA’s decision.
He pointed to a clause in the contract between Nidco and OAS, which stated that all legal disputes would be dealt with through arbitration before the LCIA.
However, Nelson also maintained that Justice Seepersad’s criticisms of the arbitration award were unfounded.
“The judge completely usurped the functions of the arbitration panel,” Nelson said.
Responding to the submissions, Nidco’s lawyer Anneliese Day, KC, claimed that the ouster clause referred to by Nelson had no legal effect based on the provisions of arbitration legislation passed by Parliament in 1939 and 2023.
She noted that both pieces of legislation state that arbitration agreements are irrevocable except by leave of a court.
“It ousts the court’s jurisdiction and is contrary to public policy,” Day said.
She also claimed Justice Seepersad could not be faulted, as the arbitration panel’s decision was inconsistent with the evidence presented before them.
“These findings are completely irrational,” Day said, as she noted that the panel found that OAS did not demobilise before the contract was terminated was contrary to its own admissions over moves to retrench staff at the time.
“The documents relied on showed the opposite,” she said.
She claimed that OAS’ efforts to renew performance bonds was an attempt to avoid the termination of the contract for abandonment.
In early 2011, OAS was awarded the contract for the project, which was then estimated to cost approximately $5.3 billion.
After the contract was terminated in 2016, the project was put on hold for several years before being restarted with local contractors.
In August 2021, Nidco announced that the project was three-quarters complete.
However, several months later, a segment of the highway at Mosquito Creek collapsed.
Delivering a decision on a partial final award on April 16, 2022, arbitrators John Fellas, Adam Constable, KC, and Andrew White, KC, upheld OAS’ arbitration claim against Nidco and ordered US$126.3 million in compensation.
In the 223-page ruling, the arbitration panel ruled that Nidco was wrong to have terminated the contract based on the two main grounds it claimed.
In the arbitration proceedings, Nidco claimed that Constructora OAS effectively abandoned the project in late 2015 after it slowed down work, dismissed most of its staff, and became insolvent by letting debt accumulate to suppliers and contracts.
The company denied any wrongdoing, as it claimed that the issues raised by Nidco were due to the fact that it (Nidco) failed to make a major interim payment under the contract.
It claimed that at the time of the termination, it had injected a further US$31 million into the project and had renewed its performance and retention bonds.
In upholding OAS’ case, the arbitration tribunal ordered that it be paid US$127,072,326 in damages minus the US$706,426.70 offset granted to Nidco.
The damages represented the company’s claims for performance and retention securities, a series of unpaid interim payment certificates (IPCs), materials in stock, temporary works, and contracting equipment.
In his judgment, Seepersad pointed to various areas of the award where he found the tribunal failed to put forward a position, properly evaluate, or make a finding on the evidence and contentions put forward by Nidco.
“The tribunal had an obligation to critically review all the information before it and to explain why the claimant’s arguments and evidence were rejected. However, the award does not reflect that such a measured evaluation of the evidence was engaged,” Seepersad said.
Nidco was also represented by Jason Mootoo, SC. Gregory Pantin and Miguel Vasquez appeared alongside Nelson for OAS.