Delayed payments, working in high-risk areas and failure to implement the procurement legislation have been plaguing contractors in T&T.
The three issues–the major one being the billions owed to them–have affected contractors so badly that some have lost their businesses, others are struggling to get by, some are tied up for years in court battles which they eventually lose and are forced to pay costs, while others have died waiting to be paid for jobs completed. In 2018, then president of the T&T Contractors Association (TTCA) Ramlogan Roopnarinesingh estimated that $4 billion was owed to the entire industry and not just to TTCA members.
The construction sector, which has historically been one of the main drivers of T&T’s economy, has had its share of challenges over the years, and the decline of the economy over the last few years has only exacerbated the problems.
The situation has been described as “daunting”, and the Government–the largest employer of construction services, through its state agencies, special purpose companies and ministries–has been accused of “dereliction of its contractual obligations” to the people in this sector.
The issues plaguing the sector were identified in a document prepared by the Construction Management Institute of T&T (COMITT) researchers Anton Balfour, R Patel and Derek Outridge under the MSc Construction Management programme at the University of the West Indies (UWI), Department of Civil and Environmental Engineering.
COMITT, recognising the urgent need to address these issues, submitted the document to the Government just before the national budget when the public and private sector were invited to share ideas on rebooting T&T’s economy.
According to COMITT, they conducted three research studies between 2015 to 2020 and held open “Think Tanks” to study the results. The “Think Tanks” attracted key stakeholders including representatives from state agencies, the Contractors Association and consultants among others.
CHASING PAYMENTS
A “Think Tank” hosted by COMITT in 2019 revealed that a major issue was untimely payment from the Government of T&T resulting from the bureaucratic payment procedures, inadequate funding, and irregular release of funds from the Ministry of Finance.
Large sums of money are owed to contractors and there has been no significant improvement to the delayed payment issue over the past decade. This has negatively impacted contractors who face low cash flow, downsizing, adverse effects to the supply chain, and insolvency amongst several other issues which have crippled some operations.
To compound the situation, there is poor governance and lack of legislative systems or Prompt Payment Laws in T&T, which mandates government agencies in other countries to pay the prime contractor on a project no later than 14 days after receiving an invoice for a progress payment. And, because there is no policing of delayed payments, the contractors and the industry overall suffer.
Some of the causes of delayed payments are as follows:
• Multi-headed client funding arrangements
• Untimely receipt of funds from the client ministries
• Lack of adherence to the payment terms by the client ministries
• In cases where the client ministries are required to request funds from the Ministry of Finance, this process is extremely time-consuming
• Bureaucratic payment approval process at the client ministries and MOF
• Lack of client funding due to re-prioritising of budgets and projects reviews
• Client transfer of funds process (client and MOF), undertaken in instances where there is insufficient funding for a project in an allocation or the allocation was used for other priorities
• Lack of awareness on the part of the public servants at ministries on the importance of timely payment processing
The implementation of Prompt Payment legislation or Statutory Adjudication is recommended to ensure the sustainability of small, medium and large contractors.
DERELICTION OF CONTRACTUAL OBLIGATION
COMITT referred to a 2020 study and provided statistics to show the contractors’ woes. (In this investigation 75 questionnaires were sent out to contractors and 65 responded; 11 large, 27 medium, 27 small.):
• 88 per cent spent more than two hours per day wasted chasing up late payments
• 88 per cent experienced a reduction in business profits
• 90 per cent were caused to pay suppliers late
• 93 per cent experienced difficulty in getting materials and services
• 82 per cent had to increase construction costs
• 88 per cent had to borrow additional funds to complete projects
• 60 per cent were unable to pay staff or to pay staff late
• 71 per cent had to suspend works due to delayed payments
• 60 per cent lead to the abandonment of works
The researchers pointed out that while there has been a “dereliction of contractual obligations” by the Government, contractors are afraid of being blacklisted. However, they noted, since the 2016 court decision in the Attorney General v Bynoe Rowe Wiltshireth where the court upheld the four-year Statute Bar, contractors seem to have changed how they seek to resolve the issue of delayed payments.
In a research done in 2015 by Charles-Ragoo (Questionnaires were sent out to 91 contractors and 71 responded; 29 large, 21 medium, 21 small), 50 per cent of contractors did not want statutory adjudication. This changed in the Bissoon 2019 study (Questionnaires were sent out to 100 contractors and 80 responded; 66 medium, 14 small) where 86 per cent of contractors preferred this method.
In respect of Prompt Payment Legislation, in 2015 only 51 per cent of contractors favoured this as a solution. In 2019, however, 86 per cent of the contractors favoured this method.
Contractors offered solutions to the delayed payment problem. The statistics from research by Bissoon (2019) highlighted the following measures used by contractors to curb the effects of delayed payments:
*59% stated they will increase their tender bids
*50% say they will decline to bid
*61% indicated they will reduce their rate of work
*65% stated that it will increase their debt financing
*67% were in agreement to work suspension
*81% stated they would extend their time for completing the works
*82% preferred upfront advanced payments for works
*82% were in agreement to contracting on mandatory payment terms
*70% preferred litigation (Bissoon 2016)
COMITT said it was of critical importance whether the Government has the funds for the project. The researchers said the budget performance was critical and should be analysed based on revenue vs expenditure. They also said the Ministry of Finance release of funds should be based on project priority levels and done on a timely basis.
The research recommended that a 20-year priority plan similar to the Canadian model be implemented. This assures the continuity of projects and payments
The Uff and Thornhill report
The Uff and Thornhill (2010) report on the construction sector in T&T made the following recommendations to curb delayed payment practices:
*Standardisation of contracts to govern local projects adopting the standard UK and international forms used for adjudication.
*The Establishment of a Specialist court in T&T modelled after the commercial courts in London to handle construction cases.
*Establishing a new Arbitration Act and Prompt Payment Legislation.
*Employing fair payment practices.
*Utilising Government bonds to facilitate legitimate payment to contractors for completed works.
HIGH-RISK WORK
Working in high-risk areas has also posed a challenge in the construction industry. They said assets of a construction site (equipment, materials and human resource) have always been exposed to threats of looting and external damage and need to be protected.
The researchers pointed out that within recent years, the geographic locations referenced as high risk (influenced by rogue elements/illicit activities) have expanded from Laventille, Maloney, La Horquetta, Beetham and Enterprise to name a few, to areas such as parts of Arima (O’Meara Road), Moruga Road (Petite Café) and Diego Martin 7 (Santa Cruz Road), exposing construction projects in these locations to increased illicit activities.
The increased cost for this risk impacts the feasibility of a project, they said, and must be considered since the risk can be covered by the client (use of joint police and army security posts in the vicinity of project zones), shared between client and contractor (provisional line item in the Bill of Quantities for site security Off duty Police or Private Security, ie, cooperative efforts), or transferred to the contractor (inclusion of a lump sum line items in the Bill of Quantities to address site security).
They also suggested involving the community to assist or keep an eye out as if left unchecked it becomes an increased cost to the taxpayers.
The researchers said these recommendations can be explored and recommended the undertaking of academic research on the subject matter.
PROCUREMENT LEGISLATION
The procurement legislation of T&T seeks to provide an efficient and equitable system for procuring and disposing of state assets consistent with proper commercial practices and promotes transparency, accountability and value for money.
According to COMMIT, with the vast level of corruption and unfair handling of state assets at the expense of the public purse, the urgency for the implementation of the procurement legislation is high. And they are pleading with the Government to do so before the end of this year.
The procurement legislation includes the application of the principles of value for money, transparency and accountability reflected by purchasing best practices in a level playing field, probity and transparency of transactions, risk management; Promotion of good governance generally through the operation of the principles of transparency and accountability in procurement of services and assets disposal; Support for local industry and business enterprises in a manner that is consistent with international obligations; indisputable public and internal confidence in procurement practices of T&T.
–reporting by Raphael John-Lall