Senior Reporter
sascha.wilson@guardian.co.tt
The Ministry of Works and Transport has started repair works on five major breaches along the banks of the New Cut Channel River in South Trinidad at a cost of $10-$12 million.
Works and Transport Minister Rohan Sinanan revealed this yesterday at the ministry’s Drainage Division Tulsa Trace pump site in Penal.
Sinanan also planned to visit areas in Erin, La Brea and Cedros yesterday, but residents who gathered at the riverbank in Woodland were disappointed he did not visit them.
In an interview with reporters, Sinanan recalled that the breaches on the riverbank occurred following recent heavy rainfall.
“We did promise the residents once we find the engineering solution to it, we will start, and this morning, after the tender process and after the evaluation, the contractor has mobilised to start to attend to five of the major breaches on the riverbanks,” Sinanan said.
This came days after residents and community groups built a tyre barrier to block a breach site along the riverbank in Woodland.
“We did ask the residents to sort of desist from using these tyres and so on and these temporary things that we know will not hold out, but thankfully this morning, we are able to start the project to repair the areas on the banks that would have been breached,” Sinanan said.
Asked if the ministry would be breaking down the tyre barrier, he said the ministry’s actions are limited and their focus is on fixing the breaches.
“We are asking everyone to work along with us. We do have the interest of all the residents. We have to work within the law, one, and two, do things that is sustainable,” he advised.
He assured that if other breaches are detected while the work is ongoing, they will also be repaired “rather than wait for something to happen.”
Estimating that the project might be completed in “just over a month,” he said the challenge was to find a way to get the material to the bank, since there are no access roads to the compromised areas.
Commenting on complaints that works should have been done in the dry season, the Minister said the ministry began an aggressive drainage and paving programme at the beginning of January. Sinanan said they initially earmarked 500 projects in the drainage programme, which had increased to 524, and they are way ahead of their 2022/2023 programme.
Explaining that a lot of technical work is involved, he said people often say the ministry should clean the entire length of a river, but to clean and rebuild a riverbank would be equivalent to their drainage budget for three years.
“So, we have to prioritise areas,” he explained.
He said they are also upgrading pump sites and flood gates with modern infrastructure in the country.
While the ministry does its part, he said citizens ought to be educated on how they can help mitigate flooding.
Noting that countries with the most modern technology are also experiencing flooding, he said Trinidad would not be spared.
As for the advice from the public on flooding solutions, he said, “I don’t know where these ideas come from but I think if they find themselves in my shoes one day and they understand how it operates, they will realise these pie in the sky solutions are nice dreams but getting in into reality takes some doing.”
He said the ministry has been paving roads in the country every day and every night.
“All cannot be done at the same time because we are working with a programme and we are working on a budget, but the idea is to repave every single road in this country on a programme and a phase basis,” he explained.
Meanwhile, South Oropouche Riverine Flood Action Group president Edward Moodie told Guardian Media over 50 Woodland residents were waiting for Sinanan.
“We saw a lot of equipment come down last night, some went down Tulsa Trace, and the guys were instructed to clear the bank until the team from the ministry come down. Unfortunately, they found out we were here, they never showed up. We even had lunch prepared for them,” said Moodie.
While the equipment was on site, Moodie was not confident the work would be done properly and all the breaches addressed.
“The situation that we face today is that the breaches are going to continue. We have two more big breaches higher up as well as nine that is about to happen and a total of 23 that have started to fail along the riverbank,” he said.
Warning of devastating consequences for the community, he said, “If we get rainfall for more than two days, the people of Woodland would have to run for their lives. This is a disaster waiting to happen.”
On Monday, Moodie, other community groups and residents had built a 40-foot tyre barrier along the bank in an attempt to block the river from spilling into the community.