Tobago Correspondent
The new terminal at ANR Robinson International Airport expansion project could be completed sooner than originally planned.
Although the terminal was set to be ready by the end of the first quarter of 2025, National Infrastructure Development Company Ltd (Nidco) chairman Herbert George now believes it could be finished earlier, possibly in the first part of that quarter.
The billion-dollar project, constructed by China Railway Construction, is being managed by the Nidco.
George has not committed to a specific date but agrees that there is noticeable advanced progress each week.
During a visit to the construction site yesterday, Guardian Media observed the larger of the two buildings was approximately 95 per cent completed, with workers seen handling smaller tasks on the nearly completed building.
Outside, landscaping at the main entrance is underway, with a newly planted roundabout and nearly completed fencing along the parameters.
According to George, the project remains on budget and has faced no major setbacks.
“It’s not just a shell,” George said. He added, “All the equipment has to be in and commissioned, so you have work going on within the terminal you are looking at. Those are the works that are being done now.
“We are working towards having it done, having it completed no later than the first quarter.”
In September, the Prime Minister gave Parliament an update on the project. He noted that payments to date to the main contractor total US$65 million, not including land acquisition costs of approximately $300 million. There was an initial delay to the project due to the COVID19 pandemic.
At the contract signing ceremony for the airport expansion project in January 2020, Finance Minister Colm Imbert said a total of $1.2 billion would be spent on the construction of a new airport terminal in Tobago, along with an upgrade of existing facilities and the acquisition of land in Crown Point to complete the expansion.
He said the new terminal was expected to cost $870 million, while $36 million would be spent to upgrade the existing airport terminal. The Government allocated $300 million to acquire 53 acres of land between Store Bay Local Road and the airport perimeter fence in the Bon Accord area.
The airport expansion contract, which was initially expected to take two years to be completed, four months for design and 20 months for construction. At the signing ceremony, Imbert said China Railway’s bid was the only compliant bid at the end of the tendering process.