Senior Reporter
derek.achong@guardian.co.tt
The Privy Council has upheld two consecutive decisions by the local courts over their ability to award compensation for unauthorised state contracts.
Delivering a majority judgment on Tuesday, Lords David Kitchin, Nicholas Hamblen, Andrew Burrows, and Lady Vivien Rose dismissed an appeal brought by the Office of the Attorney General against Trinsalvage Enterprises Limited.
Lord Michael Briggs provided a dissenting judgment in which he disagreed with the findings of his colleagues and the local courts.
Guardian Media understands that the case set an important legal precedent that is now expected to be utilised in several pending similar cases before the courts.
The case centred around a $5.75 million contract awarded to the company in 2000 for the development of the San Fernando Harbour.
The company sued the State after it completed the work and was not paid.
The State contended that the contract was not valid as the then permanent secretary in the Ministry of Works and Transport did not have the authority to approve it as contracts valued over $1 million fall under the provisions of the Central Tenders Board (CTB) Act and the purview of the Central Tenders Board.
Delivering his initial judgment in January 2014, High Court Judge Frank Seepersad agreed that the contract was null and void due to the then-permanent secretary overstepping her remit.
However, Justice Seepersad still ruled that the company was entitled to payment as the State had been unjustly enriched through the contract irregularity.
As part of his judgment, Justice Seepersad ordered the parties to agree on an independent expert to assess the work performed by the company on the project and decide on the appropriate compensation for it.
In 2019, Appellate Judges Nolan Bereaux, Prakash Moosai, and Judith Jones dismissed an appeal from the AG’s Office and upheld Justice Seepersad’s decision.
In considering the case, the Privy Council accepted that the contract was void but had to decide whether the company’s claim for unjust enrichment stultified the statutory policy of the Central Tenders Board Act.
In their majority judgment, the four Law Lords noted that the legislation did not expressly exclude claims for unjust enrichment in circumstances where contracts were awarded in breach of it.
Dealing with the policy conferred by the legislation, they said, “The policies can be said to be: ensuring value for money so that public money is not wasted on arbitrary and self-serving contracts; minimising the risk of kickbacks, financial impropriety, and unwarranted favouritism; ensuring a transparent and fair process; and discouraging or deterring non-compliance with the act.”
“In the Board’s view, allowing the restitutionary quantum meruit would not stultify those policies,” they added.
They also noted that the State was unable to adduce evidence that the contract was awarded to the company through collusion.
“In any event, if there was any evidence of bribery and corruption, that would trigger criminal offences and the possible defence of illegality to the claim in unjust enrichment,” they said.
They also rejected suggestions that the dismissal of the appeal would encourage contractors to circumvent proper procurement procedures to benefit from it.
“To rely on a restitutionary quantum meruit would be a massive risk not least because until the work had been substantially performed, there could be difficulty in establishing that the defendant had been enriched and, until that point in time, the contractor would have no redress (because there would be no valid contract,” they said.
As part of their decision, the majority noted that one week before the appeal was heard by them, the Public Procurement and Disposal of Public Property Act was proclaimed.
While they noted that the new legislation repealed the CTB Act, they noted that such did not affect their decision as the new legislative regime does not have a retrospective effect on procurement which occurred prior to its proclamation.
In his dissenting judgment, Lord Briggs ruled that the company should not be entitled to sympathy for being unaware of the requirements of the CTB Act.
“Any firm seeking government work ought to be familiar with it, just as it ought to know the requirements of health and safety legislation or the impact of public liability,” Lord Briggs said.
The redevelopment of the area surrounding King’s Wharf in San Fernando, that the company participated in almost two decades ago, has been proposed by several successive governments.
In 2019, Cabinet approved the $1.59 billion San Fernando Waterfront Redevelopment Project.
The initial phase includes the upgrade of the Plaza San Carlos Historical District, the reclaiming of 3.8 hectares of land at King’s Wharf and the relocation of the Public Transportation Service Corporation maintenance facility, and squatters along the former Trinidad Government Railway line.
The company was represented by Ramesh Lawrence Maharaj, SC, Anand Singh, Mandavi Tiwary, Vijaya Maharaj, and Michael Rooplal. The AG’s Office was represented by Thomas Roe, KC.