History is replete of examples of national, state, and private sector projects that have been dismal failures. In the case of the private sector projects the shareholders/investors bear the loss and in the case of national and state projects the population/taxpayers bear the loss. From the lessons learned from a review of major mega projects the failures can oftentimes be traced to a weak decision-making process.
A review of the Flyvberg Database For Project Cost Risk1 which assesses the risk of cost overruns for 25 different project types based on a review of 16,000-plus projects, for the category of oil and gas projects the base rate cost overrun is 34 per cent with a 19 per cent chance that the actual overrun will be 121 per cent. In a very globally competitive sector like oil refining, getting close to a 34 per cent overrun on costs is likely to drive a project into failure far less for an overrun of 121 per cent.
We don’t have to look far to see the unfavourable outcome of the Niquan GTL (Gas to Liquids) facility substantially driven by an underestimation of the technical/commercial risks and consequent challenges which led to a very significant cost overrun. The GTL plant is in receivership for a second time and deep in debt after burning through greater than US$300 million on failed restart. This has resulted in significant financial fall out for employees, local banks, insurance and investment companies, contractors and service companies and several state entities including NGC, T&TEC, WASA and TPHL.
The Pointe-a-Pierre Refinery has had its fair share of project challenges. Originally scheduled to be finished in 2008, its Gasoline Optimisation Programme (GOP) original budget ballooned to US$1.88 billion (TT$12.1 billion) from US$430 million. This was the figure given in an internal Petrotrin newsletter in 2005, which envisaged that the construction of the four new units would have lasted three years. The actual cost overrun is 337 per cent.
The project was finally completed in 2014 with the commissioning of the upgraded Fluid Catalytic Cracking Unit (FCCU) and the associated alkylation and spent acid regeneration plants. The FCCU was mechanically completed in 2013 however commissioning was delayed initially because of the OWTU challenging the integrity of the plant’s main fractionation column, thereby requiring an independent fit-for-service assessment.
The Ultra Low Sulphur Diesel (ULSD) plant which was part of the refinery clean fuels programme to complement the GOP after mechanical completion couldn’t run due to significant structural design issues which required expenditures more than US$200 million to correct a facility that had a budgeted total installed cost of just under US$400 million
Regionally, there was a recent attempt to restart the St Croix Refinery and below is an excerpt from a July 15, 2021 Reuters article.
“Investors Balk As Bankrupt St. Croix Refinery Needs $1 Billion To Be Viable
“The Limetree Bay refinery, which landed in U.S. bankruptcy court on Monday, needs at least $1 billion to finish a massive overhaul to continue as a viable operation, according to bankers, lawyers and restructuring specialists involved in the case, stacking the odds against the Caribbean facility resuming operations.
“The St. Croix-based facility’s owners burned through US$4.1 billion to resurrect what was once the largest refinery in the Western Hemisphere, hoping to take advantage of rising global demand. Instead, the refinery only operated for three months before US environmental regulators shut it in May due to foul odors and noxious releases that harmed nearby communities.”
Root cause analysis
Governments worldwide are notorious for not developing a national database of critical reviews of failed projects that identify root causes of failures and the lessons learned which can be available to the future decision makers and the public. The goal often is often to bury any information on these failed projects to avoid any negative political fallout.
For this very important national decision on the restart of the Pointe-a-Pierre Refinery the following decision process is proposed for consideration.
Decision Process
Staged Decision Process – Bad outcomes can always be traced to bad decision processes. The principle “think slow act fast” has proven time and time again to be part of the winning formula of a robust decision-making process.
The review team that is assembled and led by former energy minister, Kevin Ramnarine if not already doing so, should consider a staged decision process that first starts with a clear assessment, why restart?
That team should also be charged with the responsibility of providing feedback to the population through a public consultation process on the outcomes of their assessments of the costs , benefits and risks to the Trinidad and Tobago and their recommendations. Comments received should be addressed and any recommendations appropriately adjusted based on feedback.
Stage 1 – Why Re-start?
This assessment at minimum needs to include:
* A careful long-term study of the markets (particularly the Atlantic and regional), refinery utilisation rates, the level of competition in these markets for refined products, and most importantly the underlying assumptions. Utilisation rates correlate with refinery gross margins. High utilisation rates enhance profitability whereas low rates threaten profitability;
* The products revenue in the market segments, the cost structure of the refinery and the performance required to be achieved to be competitive on a sustained basis;
* The ability to generate sufficient free cash flow (FCF) after recovering restart costs to meet the demand for capital to compete in a very capital-intensive business that is subject to product quality and regulatory changes over its economic life;
* An obvious critical element is the long-term availability and security of competitively priced crudes, delivered to the refinery gate, that are compatible with the refinery cracking technology. There is an understanding that studies were done by Shell Global and McKinsey in the lead-up to the GORTT decision to cease operations of the refinery and offer the assets for sale or lease. There is no doubt that the review team will review the reports of these studies and augment appropriately as they see fit with other those of other consultants, Solomon Associates, Wood Mackenzie and Bank of Nova Scotia.
The assessment should also importantly identify and address any indirect negative impacts (downside risks) to T&T from a restart. The following list is not exhaustive but should be considered as a minimum requirement:
* Utilities - Considering the natural gas and water supply shortfall, the review team’s assessment should also factor in the opportunity cost of the refinery’s natural gas, electricity and water supplies and reliability of these supplies on the refinery performance. It should also address what capital expenditures are required if these resources are partially or fully not available.
From information available from various public sources the refinery needs at least 60 MMscfd of natural gas. It needs water beyond what is available from its own reservoirs, and it needs close to 100 MVA of electrical power. It is common knowledge that the country’s natural gas supply currently falls short of demand and natural gas prices have been rising due to higher costs of production. Water supply to the refinery was at best marginal requiring supplemental supply from the E&P producing fields and switching to saltwater cooling on overhead condensers with adverse effects on plant reliability and maintenance costs. Water quality was also variable with seasonal changes affecting boiler feed water quality, efficiency, and reliability. It is also common knowledge that the national water supply just meets current demand which some contingency.
*Impacts to Heritage and Paria - Both Heritage and Paria are currently generating profits which are being used to repay the principal and the interest on the former Petrotrin US$850 million bond. If the refinery is restarted, will these profitable entities be negatively impacted and if so, what happens?
Further, as Paria was an integral part of Petrotrin refining and marketing business, the assessment should include the commercial and operational relationship between Paria and the new refining company and the Pointe-a-Pierre port’s capability to handle conceivably both the storage and export of Heritage crude and import and storage of foreign crude for refining.
* Environmental Considerations - Who will be responsible for legacy environmental liabilities and how will future liabilities be delineated and addressed?
* Safe Operations –The attempts to start up the Niquan GTL facility resulted in two major incidents, the first an explosion and fire due to over-pressure and rupture of a process vessel during start-up operations and the second, the fatality of a maintenance employee working on the plant while shutdown.
Then there was the loss of four lives after completing repairs to a 30-inch sealine riser at No.5 Berth Pointe-a-Pierre port which was well reviewed and investigated by the Commission of Enquiry (CoE).
The CoE exposed management and the contractor ignorance of the differential pressure (delta P) hazard working on submarine pipelines and failure to follow management-of-change protocols after changing the agreed work method.
The Pointe-a-Pierre refinery of course is much larger and very complex. Assuring safe operations for a restarted refinery is going to be of paramount importance. As a refinery restart most likely will be phased, there will be multiple work fronts concurrently on the various utilities and process plants at different stages of the restoration, commissioning and operations cycle.
Efficient scheduling and effective coordination and communications across the site will be critical for a safe and successful restart. This requires strong leadership, a robust process safety culture, strong systems and processes and trained and competent people.
Do we still have the competent human resources available, and will any potential investors provide the critical resources to assure safe operations?
Does the Ministry of Energy and Energy Industries, which is the regulator, have the resources and capabilities to review the plans for restart and provide the necessary checks and balances for safe operations assurances?
The Lime Tree Refinery in St. Croix, mentioned above, provides a cautionary tale. It was shut down three days after restart because of a significant operational issue on February 4, 2021, when a toxic plume quietly flowed from the refinery’s flare stacks and showered oil droplets on the surrounding neighborhoods.
* Iso-butane Availability – Prior to shut down of the refinery, iso-butane was provided by PPGPL. Since that time there has been a continued reduction in the production of natural gas liquids by PPGPL due to a combination of lower natural gas volumes for processing and the liquid content of the natural gas.
Is there sufficient iso-butane to meet the needs of the Alkylation Unit or would there be a need to import supplemental supplies of iso-butane?
The assessment should also address the alternative uses for the Pointe-a-Pierre refinery and its assets/liabilities. For example, could the new plants or process equipment be sold and the “refinery safely decommissioned “and the site repurposed for another type of industry.
If there is a compelling and robust economically viable case from Stage 1 to restart the refinery, with a clearly identified plan to mitigate any downside risks, then the process can move the next stage of selecting a suitable entity to own/lease and operate the refinery. That’s next week.
The three authors of this piece indicated that they prefer to use a pseudonym so that readers can focus on the message rather than the messengers.