Senior Reporter
dareece.polo@guardian.co.tt
Prime Minister Dr Keith Rowley has dismissed Opposition leader Kamla Persad-Bissessar’s accusation of mismanagement of public funds on the ANR Robinson International Airport Development project, which she claims has incurred $431 million in cost overruns due to excessive delays.
Persad-Bissessar made the claim at a UNC cottage meeting in Las Lomas on Monday night, where she alleged that Mott MacDonald, an engineering and development consultancy firm engaged by the Ministry of Finance, had highlighted several concerns in its evaluation of the project.
Contacted yesterday, however, Rowley said, “I don’t wish to engage the Opposition Leader in any of her search for relevance.”
According to the report, which Guardian Media reviewed, three main issues emerged as the most significant factors impacting the project’s progress:
1. Lack of balance between control and risk allocation coupled with deficient risk management by all parties. These issues point to a lack of experience in terms of managing “turn-key” contracts and almost non-existent previous airport construction and commissioning experience.
2. Lack of proper contract incentives to achieve objectives. These issues point to deficient drafting of the contractual structure and the failure to consider the main objectives of the project.
3. Claims Resolution (amongst others Structural Design) - It points out a lack of effective Project Management, impacting the past and weighing heavily on the way forward.
Other issues included a lack of continuity of project roles, introducing different resolution criteria, responsibility and liability as well as reporting inconsistencies conspiring against decision making. Mott MacDonald said it received five different programmes between December 2023 and January 2024. Programme inconsistencies and long lead procurement schedules were also flagged.
The report also said NIDCO dismissed its oversight consultant, CEP Ltd, in July 2022, further hindering the project’s progress.
Persad-Bissessar claimed the firm was contracted for $27,675,075.94 and was fired for refusing to “rubber-stamp” substandard work to enable a soft opening of the airport early next year. She suggested it was a strategy to secure political advantage ahead of the general election.
She supported her claim by referencing a report by construction consultancy firm Gleeds, which said based on timelines provided by the contractor, China Railway Construction Caribbean Company Limited, and the Airports Authority of T&T, commissioning activities are expected to be completed by June 23, 2025.
In the report, Gleeds warned against hosting a soft opening before the contractor’s commissioning, testing, and training period, scheduled to conclude on March 31, 2025.
“So, the Government is trying to rush the opening of that terminal without adequate testing and commissioning of the equipment. I can tell you that they will not make the deadline to open the terminal next year. Do you know why? China Railway has now informed the Ministry of Finance that it’s experiencing serious cash flows due to increased costs and pending claims and if these are not immediately addressed will cause further delays in completing the project,” Persad-Bissessar said.
She said Finance Minister Colm Imbert, on receiving that complaint, proposed that all payments for variations categorised as approved, instructed and anticipated, totalling approximately US$14.2 million ($96.5 million), be paid to China Railway for variations which further ballooned the price.
She warned that a UNC government would hold anyone found committing this act accountable.
Alleging insufficient oversight, Persad-Bissessar condemned NIDCO’s management of the project.
“From the start, the project was massively overpriced,” she said, acknowledging that it was initially priced at $1.28 billion and rose to $1.7 billion because of cost overruns.
Mott MacDonald suggested removing NIDCO from direct management and bringing in an international firm with expertise in airport construction.
As of December 2023, a preliminary assessment revealed the project faced a 26 per cent cost overrun compared to the original contract price, along with a 131 per cent delay in the completion timeline.
Persad-Bissessar said by September, the project had already cost taxpayers $702.5 million and with land acquisition and consultancy expenses totalling $251.76 million, the overall expenditure, including land costs, would amount to $954 million.
Works and Transport Minister Rohan Sinanan and Minister in the Ministry of Finance Brian Manning deferred comments on the claim Imbert, with the latter saying Imbert will issue a detailed press release.