There is conflicting information about the last time the Port of Port-of-Spain was dredged. According to Minister of Works and Transport Rohan Sinanan, the port was last cleared in 2000, which is approximately 20 years ago.
“This dredging was long overdue,” Sinanan said
“This was due since 2013, unfortunately, three tenders were aborted,” Sinanan continued.
But former Minister of Works and Transport Jack Warner said when he was in office (2010-2012) the port was dredged in 2011 by a local company. He said before that dredging was done in 2005.
“It was dredged by a company called Kardway Contractors,” Warner said.
“I don’t want to get in any banter with the minister but that is the fact,” he continued.
However, like Sinanan, Warner believes that dredging of the port is long overdue. He said ideally the port should be cleared every two years.
A Dutch company called Dutch Dredging won the bid for the project and is currently working 24/7 to get the job done by month’s end.
“This contract should be completed by the end of January,” Sinanan said.
The project cost the Government 60 million dollars but according to Sinanan, there may be some cost-cutting. The Works Minister said because dredging was not done for so long the Tobago Cargo vessel was not able to operate where it was supposed to. However, the minister said after this project is completed the port would be able to accommodate all the inter-island passenger and cargo vessels including the new vessels scheduled to be built later this year.
Sinanan said dredging is an ongoing exercise and because it wasn’t done for so long it prevented some vessels from coming into T&T.
“We do have large vessels who want to come into Trinidad and they can’t because of the amount of silt built up,” Sinanan said.
“The long term plan is for all the Tobago vessels to berth here to free up the port for international cargo and cruise ships,” he continued.
In a press conference after the Dredger ship tour, the Minister and Officials at the Port Authority announced that the MV Jean De la Valette which started servicing the sea-bridge in July 2019 will go for maintenance from January 24th to February 4th.
In its absence, two passenger vessels the Galleons Passage and T&T spirits will work the Trinidad and Tobago route.
The minister also announced that the port is currently in negotiations to upgrade the equipment used there.