Senior Multimedia Journalist
joshua.seemungal@guardian.co.tt
Construction company China Jiangsu International Corporation Trinidad and Tobago Limited has been ordered by the High Court to pay the Housing Development Corporation (HDC) more than $30 million in damages related to the controversial HDC Las Alturas Project.
China Jiangsu was awarded a contract of $67.62 million by UDECOTT in 2003 to construct 297 apartments which started in 2004 along Lady Young Road. When UDECOTT refocused on non-residential development, that contract was transferred to the HDC in 2006.
The case dealt specifically with the structural damage to building blocks ‘H’ and ‘I’ of the project. That phase of the project started in 2008 and ended in 2010. As a result of land slippage that damaged the structure of the blocks, the buildings that cost around $26 million to construct were eventually demolished in 2012 at a further cost of $3.3 million.
The judgment comes more than seven years after the HDC filed a claim for damages for breach of contract and negligence concerning the construction of apartment and townhouse units located at Stephenville Road, Morvant.
On April 19, High Court Judge David Harris ruled that China Jiangsu International T&T must pay HDC $26 million, representing wasted expenditure on blocks ‘H’ and ‘I’—specifically, payments made to China Jiangsu; $3 million for the cost of carrying out site instruction 73 to demolish and make good blocks ‘H’ and ‘I’ of the project; $500,000 representing the installation by Trintoplan of three piezometers and six inclinometers; $110,000 representing hoarding off-site; US$55,000 representing consultancy fee paid to Mueser Rutledge; $36,041 representing the assessment of blocks ‘H’ and ‘I’ by Trintoplan; and another $22,943 for other services.
The agreement between the parties to construct 90 apartment units and 44 townhouse units was signed in January 2008.
Before the Las Alturas deal, China Jiangsu had constructed another five housing projects for the HDC.
China Jiangsu International was also the contractor for the Tamana InTech Park project. The project, initially estimated to cost $1.1 billion, skyrocketed to $1.8 billion due to cost overruns and variations from the blueprint. The project was scheduled to be completed in 2010 but did not finish until 2014.
At a point in time, however, China Jiangsu was owed $35 million for project variations.
“What really stalled the project was the fact that the previous administration had variations with the scope of work, which was not properly documented. They deviated from the blueprint, which led to cost overruns. Another setback was a result of litigation from engineering consultants and architects. We’ve had a situation where some of them have sued because of the delays in the project,” former UTT chairman Curtis Manchoon said about the project while construction was ongoing.
China Jiangsu International also later received a $0.5 billion contract to construct the University of the West Indies South Campus in Debe/Penal in 2012, despite the fact that HDC was aware since 2011 that these two brand-new apartment buildings had to be demolished.
“This speaks to the danger of a siloed approach to national development, which the new Public Procurement law will rectify,” said chartered surveyor and former president of the Joint Consultative Council (JCC) for the Construction Industry Afra Raymond.
Former president of the Trinidad and Tobago Contractors Association (TTCA) Mikey Joseph had said it was “surprising” and “appalling” that the University of the West Indies (UWI) later approved a $509.4 million contract to build the South campus to a Chinese company with a poor track record.
A source of political debate within the PNM
The failed Las Alturas Housing construction project was a source of much political debate within the People’s National Movement (PNM) government at the time, with unconfirmed rumours that it led to disagreements between then prime minister Patrick Manning and then housing minister Dr Keith Rowley.
Andre Monteil was the chairman of the HDC at the time, and Faris Al-Rawi was a director of the HDC.
It was also a source of a bitter dispute between the PNM and the United National Congress. During the People’s Partnership government’s tenure, a Commission of Enquiry into the project was commissioned in 2014.
“So where did that money go? We have to answer that question,” then prime minister Kamla Persad-Bissessar said.
“Should the public today do as the PNM did and sweep this matter under the carpet? Should these high-profile PNM members not be able to explain what happened under their watch?”
In September 2016, the commission’s report found that there were no grounds for criminal proceedings, but recommended civil action be taken against former UDECOTT Chairman Calder Hart, Noel Garcia, UDECOTT and HDC for negligence.
Following the release of the report’s findings, Hart and Garcia took legal action. They claimed they were not informed of the adverse findings of the report and thus, did not get an opportunity to respond to the claims before its publication. Garcia later succeeded in his legal challenge against the commissioners of the Las Alturas inquiry as the High Court quashed the findings against him.
China Jiangsu also threatened legal action if it was not removed as a party in the commission.
According to Prime Minister Rowley in 2016, the inquiry that cost more than $24 million was a political witch-hunt doomed to fail. “The Government had the requirement to go after the contractor flatly and deliberately refused to do so. To add insult to injury, the same contractor failed to appear before the Commissioner of Enquiry because he was too busy building in the new contract that was given to them by the said government in this matter,” he accused.
Afra Raymond
ABRAHAM DIAZ
Raymond: We need to ensure China Jiangsu actually pays damages
According to Afra Raymond, the judgment seems to be fair, as it was a design-build contract in which the contractor is responsible for its subcontractors and consultants as part of the ‘single point of responsibility principle.’
He did, however, suggest the ruling, which took seven years, was too long. “This case is also significant since ours is a Black country which has taken proper steps to defend its patrimony against multinational contractors, Chinese in this case. That is something seldom seen, so we need to register the episode.
“We now need to be vigilant to ensure that China Jiangsu, represented by former PNM AG John Jeremie SC, actually pays the damages awarded by the High Court, amounting to $30 M.”
Raymond said the underlying lesson of the Las Alturas matter was that the Housing Development Corporation’s massive programme engenders a deeper set of conflicts.
“The demand of those on the waiting list for housing in urban locations can push the programme into costly projects on sites which have remained undeveloped, for whatever reason. In this case, an unsuitable site was used for a high-density, hillside housing development and those conflicts seeded these difficulties,” he said.
He also referenced two previous projects involving China Jiangsu International, saying that they were the contractors for ‘the long-delayed UWI Debe Project and UTT Tamana.’ The JCC headed by Raymond had stated its concerns about the Debe project in a letter of May 18, 2012, to then UWI principal Prof Clement Sankat.
Fazir Khan
COURTESY FAZIR KHAN
JCC head: We need to work out mechanisms to deregister contractors guilty of negligence
President of the Joint Consultative Council (JCC) for the Construction Industry Fazir Khan believes that a repeat of such an instance as Las Alturas can only be avoided by extreme due diligence by employers, consultants, and contractors.
He was confident that the Commission of Enquiry into Las Alturas highlighted the project’s issues, and lessons were learned within the construction industry. However, he believed the industry still needs to work out mechanisms by which contractors who have clearly been guilty of negligence are deregistered.
“There are procedures in the procurement legislation for this but some interpretation may be required by the Office of the Procurement Regulator,” Khan said.
“Procurement legislation is there to address matters of transparency and value for public money during the procurement process up to and including the award of contract. What happens in the post-contract period like in Las Alturas does not fall under the purview of the new legislation save and except for some limited aspects of performance and maintains of contractor registration.”
Timeline of the project
• In December 2002, UDECOTT acquired the Las Alturas site.
• ↓In 2003, UDECOTT, then led by Calder Hart, awarded a $67.62 million contract to China Jiangsu International Corporation for the construction of 297 apartments in Moravant–the Las Alturas Project.
• ↓In March 2005, a letter was allegedly sent from UDECOTT’s chief construction engineer indicating that there was significant movement of the lower slope of the site where blocks F, G, H and J were located. Geo Tech Associates, which was a former party in HDC’s civil case, was hired by HDC to provide geotechnical information on the site chosen. In 2007, China Jiangsu was awarded a two-year contract of $74.87 million for 134 units in 20 buildings. In January 2008, the second phase of the project was signed between HDC and China Jiangsu. Later that year, Geotech Associates prepared a subsoil investigation report for Buildings H, I and J.
• ↓Construction work on Buildings H and I began in December 2008, but less than a year later, damage on the ground floor of Building H was observed. In January 2010, buildings H and I were completed.
• ↓However, a subsequent report by Geotech determined that there was land slippage. Civil Engineering Management and Services then recommended that buildings H and I be demolished to relieve stress on the structure. Engineering consultants Trintoplan Consults Ltd also found that buildings H had to be demolished while building I would also likely have to be demolished. In the end, there were more than 100 apartment units that were paid for but never completed.